4 wells drilled at South Pars phases 6-8

Source: shana 11/28/2004, Location: Asia

Share |
TEHRAN (PIN) -– Deputy managing director of Petropars Company for offshore affairs told Petroenergy Information Network that total drilling at phases 6 and 7 of South Pars Project reached 22,961 m and 21,342 m, respectively by the end of November 20.

Ali Ne’matollahi added that Statoil Company has drilled one appraisal wells at phase 6 while three more wells have been completely drilled and tested.

The tests showed that production from each well can be increased 20-30 percent,” he said. He noted that total progress of South Pars phase 6 through 8 has reached 42 percent by the said date, adding, “Engineering and construction operations for topsides are being carried out by Sadra. The company was also in charge of building jackets for the phases, which ended August 2004.”

Development project for South Pars phases 6-8 aims at producing 80 million cu. m. sour gas, 120,000 barrels gas condensate as well as 1.2 million tons liquefied petroleum gas (LPG) for exports and the project is to be complete in 2006.

Annual revenues from the said phases will amount to 1.876 billion dollars considering 4 cents for every cu. m. natural gas.


Drilling News in Iran >>

Mongolia >>  9/20/2018 - Petro Matad, the AIM quoted Mongolian oil explorer, provides a summary of the results from its Snow Leopard 1 well: ...
Trinidad and Tobago >>  9/20/2018 - Range, an international oil and gas company with oil and gas projects and oilfield service businesses in Trinidad and Indonesia, is pleased to provide...

Canada >>  9/18/2018 - Seadrill Partners LLC ("SDLP" ) has secured a one well contract with multiple options with ExxonMobil Canada, Ltd., for the West Aquarius in Canada....
Botswana >>  9/17/2018 - Tlou Energy Limited, the ASX, AIM and BSE listed company focused on developing gas-to-power projects in southern Africa using coal bed methane ("CBM")...

Romania >>  9/17/2018 - Serinus Energy plc has announced the flow-test results of the Moftinu – 1003 well. As previously announced, the Moftinu – 1003 well was drilled to 1,6...
United Kingdom >>  9/17/2018 - Reabold is pleased to note the successful completion of the rig site survey over the proposed location for the forthcoming Wick well. ...

Related Categories: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 

Related Articles: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 


Iran Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |

Oil & Gas Projects in Iran >>

More News

 

Oil & Gas Companies in Iran >>


Related Links

AZ BD BN CN GE HK ID IN IR JP KR KZ MM MN MY PG PH PK RU SG TH TJ TM TW UA UZ VN
Gulf Oil and Gas
Copyright © Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.