Gulfsands Provides Khurbet East Well Drilling Update, Syria

Source: www.gulfoilandgas.com 3/30/2007, Location: Middle East

Share |
Gulfsands Petroleum plc provided the following update on the Khurbet East ("KHE-1") exploration well in Syria Block 26, where Gulfsands is operator and owner of 50% interest.

The KHE 1 well commenced drilling in mid February and is scheduled to take 100 days to drill and evaluate to a planned total depth of approximately 3,700 metres.

The Khurbet East prospect is a fault-bound structural culmination, with closure mapped at multiple potential reservoir levels. The well is located approximately 12 kilometres southwest of the Souedieh Oil Field and 12 kilometres south of the Roumelan Oil Field.Currently, drilling is on schedule at a depth of 2450 metres.

Cretaceous Massive Formation

The top of the Cretaceous Massive Formation was encountered at 1,917 metres and a series of drilling breaks and live oil shows were observed. The Company continued drilling to a depth of 2,203 metres and then made a decision to run intermediate wireline logs as well as wireline pressure testing and fluid recovery.

Independent wireline log analysis of the Massive interval indicates a gross oil column of some 31 metres with approximately 22.5 metres of net oil pay. The wireline pressure measurements also recorded an oil gradient across the interval. An oil sample was obtained and had a measured API gravity of 21 degrees at surface conditions. PVT analyses of the oil samples are currently being undertaken.

Chilou Formation

Prior to drilling the Massive Formation the Company drilled through the Tertiary aged Chilou 'B' Formation, which was encountered below 1319 metres. After encountering oil shows and drilling breaks that indicated potential reservoirs, the Company successfully acquired approximately 8.5 meters of whole core from within the Chilou 'B' Formation. Routine core analyses, including oil extractions and porosity and permeability measurements, are underway. Wireline logs were also acquired over this reservoir interval but due to the large hole size required in this early portion of the wellbore it was not feasible to run pressure tests or fluid recovery.

Independent wireline log analysis of the Chilou intervals indicates some 26.4 metres of net oil pay of which some 19 metres are contiguous in the top of the Chilou 'B' formation. These net oil pay figures, the quality and moveability of the oil will have to be confirmed with later testing.

Following wireline logging, 13 3/8" casing was set over the Chilou intervals to a depth of approximately 1904 metres and the Company continued drilling ahead to the Massive Formation as noted above.

The Company has resumed drilling ahead in this well in order to evaluate the underlying Triassic and Palaeozoic Formations.

Gulfsands' CEO, John Dorrier, said: "We are encouraged by the results to date in the Massive and Chilou Formations. We look forward to reaching our deeper objectives in the Triassic and the Palaeozoic Formations. However, only after penetrating these further objectives and reaching target depth will we conduct production testing operations. The ultimate commerciality of the hydrocarbons encountered at Khurbet East can only be determined after further work including production testing and appraisal drilling."

Drilling News in Syria >>

Nigeria >>  8/16/2018 - Eland Oil & Gas PLC, an oil & gas production and development company operating in West Africa with an initial focus on Nigeria, is pleased to announce...
Norway >>  8/16/2018 - Equinor Energy AS, operator of production licence 025, has concluded the drilling of appraisal well 15/3-11 on the 15/3-4 (Sigrun) oil and gas discove...

Trinidad and Tobago >>  8/16/2018 - Range, an international oil and gas company with assets in Trinidad and Indonesia, and an oilfield services business in Trinidad, is pleased to provid...
Congo >>  8/15/2018 - Anglo African Oil & Gas plc, an independent oil and gas developer, is pleased to confirm that the TLP-103 well ('TLP-103' or 'the Well') on the Tilapi...

Argentina >>  8/13/2018 - Echo Energy plc, the Latin American focused upstream oil and gas company, has announced an update on the ongoing testing programme in the Company's Fr...
Morocco >>  8/13/2018 - Sound Energy, the Moroccan focused upstream gas company, has announced the mobilisation of the National 110 IE (1500HP) land drilling rig owned by Sai...

Related Categories: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 

Related Articles: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 


Syria Oil & Gas 1 >>  2 | 3 |

Oil & Gas Projects in Syria >>

More News

 

Oil & Gas Companies in Syria >>


Related Links

AE BH IL IQ JO KW LB OM QA SA SY YE
Gulf Oil and Gas
Copyright Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.