South Pars Phase 13 First Tripod & Deck Installed

Source: www.gulfoilandgas.com 12/27/2016, Location: Asia

Share |
As reported by public relations of pars oil and gas company(pogc), Payyam Motamed, the director of development plan for phase 13, announced that tripod and flare deck of the phase 13 platform weighing 523 tones was already finalized during 4 months since the beginning of the construction in industrial yard of SADRA in June 2016.

Motamed added: steel structures in its deadline on November 11th, were loaded off the mentioned yard, and braced on the barge then transferred to offshore location of the phase 13.

He stated that it has taken 9 days to install the tripod without considering the adverse weather conditions.

Pointing to proceeding of platform construction activities and offshore equipments of the phase 13, Motamed continued that construction of the second tripod is almost finished and will be ready to install in the offshore location of 13D by February 2017.

Previously, the director of development plan of phase 13, had declared that constructing platforms and their accessory equipments had been possessed of reasonable rate in the yard of SADRA, concerning the appropriate financial resources provided by national Iranian oil company (NIOC) and the accurate supervision made by pars oil and gas company (POGC).

He also claimed: “this cycle would progress gradually by applying more merchandizes imported in the coming months”

Pointing to loading and installing the decks of B and D of the same phase by May 2017, Motamed had said:”completion of drilling before the installation, Pre-commissioning and initiation, will be ended to the maximum of five months and these platforms will be prepared to send gas to onshore refineries of the phase 13, located in the site of Akhtar.”

Development News in Iran >>

United Kingdom >>  10/18/2017 - Independent Oil and Gas plc (IOG), the development and production focused Oil and Gas Company, has signed a Letter of Intent (LOI) with Offshore Desig...
Australia >>  10/17/2017 - Galilee Energy Limited has signed a binding agreement with Jemena to work together towards agreed development milestones that will fast-track plans to...

Norway >>  10/12/2017 - Petroleum Safety Authority of Norway has given Aker BP consent to perform modifications relating to gas lift at Tambar. The gas lift project is part o...
Iran >>  10/10/2017 - A tender for developing Iran’s Azadegan oil field has been delayed again, a senior Iranian oil official said on Tuesday, adding that it will not take ...

Iraq >>  10/9/2017 - Iraqi oil minister Jabar al-Luaibi said that Chevron and Total are among the companies that have expressed interest in developing the Majnoon oilfield...
Iraq >>  10/9/2017 - Iraq’s talks with Exxon Mobil to develop a multi-billion-dollar project to boost output from several southern oilfields are nearing completion, oil mi...

Related Categories: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  Food Supplies  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Unskilled Labors  Utility Systems  Waste Disposal  Water Supply Services  Welding Products/Services 

Related Articles: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Transportation, 4X4 Trucks  Utility Systems  Water Supply Services  Welding Products/Services 


Iran Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 |

Oil & Gas Projects in Iran >>

More News

 

Oil & Gas Companies in Iran >>


Related Links

Gulf Oil and Gas
Copyright © Universal Solutions All rights reserved. - Privacy Policy.