Genesis secures new solar site in Bay of Plenty

Source: www.gulfoilandgas.com 8/14/2024, Location: Not categorized

Genesis Energy has taken another step in delivering on its commitment to solar development after securing an advanced stage, 127 MWp consented site near Edgecumbe in the Bay of Plenty. The site is expected to start generating electricity in 2026.

The agreement with New Zealand based developer Helios Energy is expected to go unconditional in Q2 FY25. The site is a quality competitive solar development which provides a high solar yield. It is in a good location connecting to an existing substation and acquired from a reliable developer. It will be wholly owned by Genesis who will take all the energy produced. Final Investment Decision (FID) will determine if it is developed on balance sheet or through another structure.

The 207-hectare site will hold approximately 220,000 solar panels and generate around 230 GWh of renewable electricity annually, enough to power around 30,000 houses. The project is expected to require a construction workforce of around 100 people and employ up to five staff when operational.

The site is consented, with grid connection agreements in place. FID is expected in mid-CY25 followed by the start of construction.

The acquisition is another proof point of Genesis' Gen35 strategy which aims build to 95% baseload renewable generation by FY35, freeing up to 1,400 MW of generation capacity at Huntly Power Station to support energy security for the country. Huntly will provide a range of generation assets and fuels to store energy for electricity generation from a minute to a month.

This is the second advanced solar site Genesis has secured following the 63 MWp site at Lauriston on the Canterbury Plains in November 2023, acquired as part of Genesis' joint venture with FRV Australia. That site is currently under construction and on track for first generation later in 2024. Other greenfield solar projects are also in the development pipeline.

Chief Wholesale Officer Tracey Hickman said Genesis is delivering on its strategy to build 500 MW of grid-scale solar by FY28.

"We're delivering strategy through a combination of joint venture, balance sheet finance, and power purchase agreements. We’ve seen through our experience at Lauriston the benefit of purchasing advanced developments and turning them from bragawatts into megawatts. With a large and diverse customer base Genesis can take opportunities for new renewables and deliver them to market quickly, while we continue to explore other sites and possibilities," Hickman said.

Edgecumbe site developer Helios Energy was founded in New Zealand in 2020 by a team with extensive global renewables experience. Helios was one of the first grid-scale solar developers to enter the New Zealand market.

Helios Energy Founder and Managing Director Jeff Schlichting said the sale of the site would support the development of Helios’ broader national solar development pipeline.

"We're pleased with this transaction and our counterparty. Edgecumbe is a high-quality solar development and Genesis is well-positioned to responsibly deliver it for the benefit of Aotearoa New Zealand and our national decarbonisation commitments."

Genesis intends to take a similar approach to its Lauriston development, using panels that allow for dual use of the land so sheep can graze underneath them.

Genesis will continue Helios' work in engaging with mana whenua, the local community and key stakeholders.

Land size ~207ha
Power generated ~230 GWh pa
Expected FID Mid-CY25
First generation Mid-CY26
Expected total project cost ~$216m (~$1.7m/MWp)
Approx. number of solar panels Approx. 220,000

Note that the final size, development costs and resulting generation is subject to final investment decision and detailed design processes.

Total project costs include EPC construction, connections, finance and leases through construction and other costs.


India >>  12/3/2024 - Tata Power Renewable Energy Limited (TPREL), a prominent player in India’s renewable energy sector and a subsidiary of Tata Power, has successfully co...
Bangladesh >>  12/2/2024 - The Asian Development Bank (ADB) has signed a $24.3 million financing package with Muktagacha Solartech Energy Limited (MSEL) to establish a grid-conn...

Italy >>  12/2/2024 - GreenGo announces the approval of three projects in the first Italian agri-voltaic tender, promoted by the Italian Ministry for the Environment and En...
Italy >>  12/2/2024 - GreenGo announces the approval of three projects in the first Italian agri-voltaic tender, promoted by the Italian Ministry for the Environment and En...

Romania >>  12/2/2024 - Econergy has announced that its 92MW solar park in Parau, Romania, has started commercial operations, marking the latest step in the company’s growth...
South Africa >>  12/2/2024 - The facility, with a net installed capacity of 50 MW, is located in the Northern Cape province and is backed by a PPA signed until 2036 guaranteed by ...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.