Equinor – Hammerfest LNG – Electrical facilities
Source: www.gulfoilandgas.com 9/4/2024, Location: Europe
The Norwegian Ocean Industry Authority (Havtil) has carried out an audit of Equinor and electrical facilities at Hammerfest LNG.
The audit was conducted from 10 to 13 June 2024.
Objective
The objective of the audit was to monitor how the company complies with the regulatory requirements for electrical facilities, and work in and operation of electrical facilities.
In addition to electrical facilities, the audit also included topics within HVAC and telecommunications.
Result
The audit identified non-conformities in the following areas:
Safety function for monitoring overpressure in pressurised rooms
Deficiencies in governing documents
Work in and operation of electrical facilities
What happens now?
We have asked Equinor to report to us by 12 September 2024 on how the non-conformities will be addressed.