Trillion Energy International Inc. (“Trillion”, or the “Company”) is pleased to provide an update on the velocity string installation program at the SASB gas field.
On October 27th the snubbing unit was positioned over the Akcakoca-3 well where 2 3/8” production tubing (“velocity string” or “VS”) was ran into the well through the existing 4 ½ tubing. The operation was completed on October 29th. The well continued to flow throughout the operation.
Following the VS installation, Akcakoca-3 production increased from approximately 2.0 MMcf/d (average production for the 27 days prior to installation) to 2.6 MMcf/d (average production first 4 days post VS). We continue to monitor production from the well at this time.
On October 30th, 2024 a 2 3/8th velocity string was ran into the West Akcakoca-1 well using the snubbing unit. The operation was completed by November 1st , where the velocity string reached a total measured depth (MD) of 3,496 meters. The West Akcakoca-1 well was not producing prior to the operation and gas production is expected to resume following nitrogen stimulation being applied.
Currently, VS is being run into the Guluc-2 well. The velocity strings are being installed with the objective of reducing water loading issues in the SASB gas wells.