Deltic Energy Provides Selene Update and Economic Model

Source: www.gulfoilandgas.com 11/14/2024, Location: Europe

Deltic Energy Plc, the AIM quoted natural resources investing company, is pleased to provide the following update in relation to the recent drilling operations at the Selene prospect in the UK Southern North Sea:

Rig Demobilisation and Well Cost Estimates
The Valaris 123 drilling rig was demobilised from the Selene site on 10 November 2024.

Following confirmation of demobilisation, the well Operator has provided an updated cost estimate for the well of USD$48M which is within the USD$49M carry cap pursuant to Deltic's farm-out arrangements in relation to the 2024 Selene drilling and testing costs. Therefore, Deltic does not expect to have any residual cost exposure to the well drilling costs.

The estimate of well costs will be subject to variation as the Operator receives final invoices from service providers over the coming months. As at 31 October 2024, Deltic had an unaudited cash balance of £1.9M.

Entry to Second Term of the Licence
Following the announcement of the Selene discovery on 31 October 2024, Shell, in its role as licence Operator, has recommended that the Joint Venture ("JV") enter into the Second Term of Licence P2437 and will now seek to agree a low-cost work programme and timeline with the NSTA to support the maturation of the discovery towards a potential Final Investment Decision ("FID") in relation to the development of the Selene discovery.

During the Second Term of the licence, the JV will complete the post-well analytical work and the various studies required to finalise a development concept. No further drilling is required prior to FID. Work will also commence on the various environmental studies to support the regulatory permitting and approvals required to progress to development.

Selene Preliminary Development Concept
Deltic has completed its preliminary reservoir modelling, and updated its preferred development concept, based on analysis of the data available from the 48/8b-3Z well. The technical work completed indicates that a potential development consisting of two horizontal wells would be sufficient to drain the majority of the Selene structure, based on the improved reservoir characteristics seen in the 48/8b-3Z well. Deltic's base case assumption is that a minimum facilities, normally unmanned, installation positioned on Selene will be tied back to the Barque field infrastructure via a c. 20km subsea pipeline. The Barque-Clipper-Bacton gathering system and onshore gas processing plant has sufficient capacity to accept the gas production from the proposed Selene development.

Deltic will be promoting this potential development scenario with its Joint Venture ("JV") partners, however ultimately the maturation of the field development plan will be led by the licence Operator and will be subject to further review once the detailed post-well analysis has been completed.

Selene Updated Economic Model
Deltic has updated its internal development success case economic model, based on cost data provided by S&P Global in 2023, for the two well development concept summarised above and in light of recent changes to the UK's fiscal regime announced in the budget on 30 October 2024.

This preliminary economic evaluation indicates that the P50 discovered volume is more than twice the minimum economic field size and in the proposed assumed development scenario, Selene would have a post-tax NPV10, net to Deltic, of $61M (50 pence/share equivalent) which supports Deltic's decision to support the entry into the second term of Licence P2437 and progress the work required to reach FID.

Andrew Nunn, CEO, commented:
"I am pleased to report that the Selene discovery well was completed safely and within the carry resulting from the farm-outs to Shell and Dana. Getting JV agreement on moving into the Second Term of the licence is another key milestone on the journey from discovery to development for Selene. It also reflects the high quality nature of Selene's reservoir and the expectation of a low cost development with enhanced production and economic potential from the asset.

This decision to move into the second term of the licence kicks off an incredibly busy period, as we support the Operator through the various engineering, environmental and regulatory workstreams that need to be pulled together to support a potential Final Investment Decision. The workstreams now in train are an important signal to our investors as you wouldn't commence this process if you didn't believe there was a material commercial return at the end it. We look forward to updating the market in due course."


Australia >>  12/5/2024 - - Drilling commenced on 5 December at the West Mereenie 29 (WM29) development well
- WM29 is the first of a two well deve...

Iraq >>  12/4/2024 - The technical and engineering staff of the Iraqi Drilling Company completed the drilling and reclamation of 12 oil wells during the past month of Nove...

Colombia >>  12/2/2024 - Canacol Energy Ltd. (“Canacol” or the “Corporation”) is pleased to provide the following update concerning its ongoing exploration and development dri...
Equatorial Guinea >>  11/29/2024 - Panoro Energy ASA (“Panoro” or the “Company”) can confirm that drilling of the S-6 (“Akeng Deep”) exploration well at Block S offshore Equatorial Guin...

United States >>  11/29/2024 - TomCo the US operating oil development group focused on using innovative technology to unlock unconventional hydrocarbon resources, announces that its...
Canada >>  11/27/2024 - Helium Evolution Incorporated ("HEVI" or the "Company"), a Canadian-based helium exploration company focused on developing assets in southern Saskatch...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.