Chiyoda International Corporation (CIC) and CB&I LLC (CB&I), the construction JV partners for the Golden Pass LNG Export Project (Project) in the State of Texas, U.S., continue to carry out work on the Project.
CB&I and CIC have continued cooperative discussions with Golden Pass LNG Terminal LLG (GPX), related to completing the Project.
On November 21, 2024, in U.S. time, we reached an agreement on the amendment of the Engineering, Procurement and Construction (EPC) contract and associated commercial terms for the completion of the full scope for Train 1*1.
CB&I and CIC, and Golden Pass LNG Terminal LLC will continue engagements on subsequently amending the contract for the completion of Trains 2 and 3*2 and will disclose promptly when we conclude such agreement.
*1 Train 1:The first train of natural gas liquefaction facilities currently under construction
*2 Train 2 and 3:The second/third trains of the facilities mentioned above