According to China Petroleum Network news on November 25, the author learned that the main installation work of 12 150,000 cubic meter storage tanks of Huajin Crude Oil Tank Area Project of Pipeline Bureau No. 1 Company has been successfully completed.
The Huajin crude oil tank area project is one of the company's three "top projects", including 12 storage tanks and 7.1 kilometers of off-site pipelines. It is also one of the key projects supported by the country to support the revitalization of Northeast China.
Since the project was built, the three tank installation units in Huajin Crude Oil Tank Area have been racing against time, and the crews have cooperated with each other and worked closely together, showing strong team cohesion. At the same time, the project department closely combined construction with the theme labor competition, which greatly stimulated the enthusiasm and creativity of the project personnel, and significantly improved the construction efficiency. It took only 27 days to successfully complete 50% of the main installation tasks, laying a solid foundation for the smooth progress of the project.
Up to now, the overall progress of the project has reached 57.5%, the main installation of 12 storage tanks has been completed, the comprehensive progress of the floating tank construction has reached 40%, and the comprehensive progress of the accessories construction has reached 55%.