Woodside’s Scarborough Energy Project advances with delivery of Pluto Train 2 modules

Source: www.gulfoilandgas.com 12/23/2024, Location: Not categorized

The Scarborough Energy Project has passed another significant milestone with the final Pluto Train 2 modules arriving at the Pluto LNG facility in Karratha, Western Australia.

The successful completion of the Pluto Train 2 module program advances the Scarborough Energy Project towards the targeted delivery of first LNG in 2026.

Since February 2024, a total of 51 modules, weighing a combined 56,000 metric tonnes, have been shipped to Karratha from the module yard in Batam, Indonesia, where they were built.

Expanding the Pluto LNG facility to include a second LNG processing train provides an efficient way to process gas from the offshore Scarborough field.

Once operational, Pluto Train 2 will have capacity to process approximately 5 million tonnes of LNG per annum.

The expanded Pluto facility includes new domestic gas infrastructure and will have the capacity to supply up to 225 terajoules per day to the Western Australian market.

Woodside selected Bechtel to execute the engineering, procurement and construction of Pluto Train 2, with construction activities at the Karratha site commencing in August 2022.

Woodside Executive Vice President & Chief Operating Officer Australia Liz Westcott said the safe and timely arrival of all modules was a credit to both the Woodside team and lead contractor Bechtel.

“The scale of what has been delivered is an incredible achievement and reflects the team’s commitment and professionalism.

“The Scarborough Energy Project has made significant progress across multiple work fronts and is now over three quarters complete.

“The Woodside and Bechtel teams will now focus on executing the module integration and commissioning of the facility in preparation for the targeted first Scarborough LNG cargo in 2026.”

“The remarkable success of the module program exemplifies the robust relationship forged between Woodside and Bechtel on the Pluto Train 2 project,” said Bechtel Energy President Paul Marsden. “This achievement reflects our shared vision and the unwavering dedication of our project team to cultivate a One Team culture. We look forward to continuing this collaborative spirit as we successfully deliver this project.”

The Scarborough Energy Project is expected to contribute significantly to the Australian economy, generating more than A$50 billion in direct and indirect tax payments. The Scarborough Energy Project is also expected to generate more than 3000 jobs during the construction phase and create or sustain almost 600 jobs on average during operations.1


Mauritania >>  2/10/2025 - Kosmos Energy announces that first liquified natural gas (LNG) production has been achieved at the bp-operated Greater Tortue Ahmeyim (GTA) LNG projec...
United States >>  2/6/2025 - Harvest Alaska (Harvest), announced an agreement with Marathon Petroleum Corporation (MPC) and Chugach Electric Association (Chugach) to bolster South...

Congo >>  2/5/2025 - The liquefaction of natural gas onboard the Tango FLNG has been monitored during the initial months of the operation. The tests have proven that the ...
Netherlands/Holland >>  2/3/2025 - EemsEnergyTerminal launches an open season for the storage and regassification of LNG after 2027 in the Eemshaven in the Netherlands. EemsEnergyTermin...

United States >>  2/3/2025 - American Petroleum Institute (API) President and CEO Mike Sommers issued the following statement on the Senate’s confirmation of Chris Wright to lead ...
United States >>  1/30/2025 - Entergy Texas reached a landmark transportation agreement with Kinder Morgan to secure natural gas supply, supporting the rapid industrial, commercial...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.