Arq Provides Update on Transformational GAC Project

Source: www.gulfoilandgas.com 2/7/2025, Location: North America

Construction of Arq’s GAC production facility remains on schedule, with initial production expected in Q1 2025
Customer negotiations for GAC contracts progressing well
GAC production ramp-up set to begin in H1 2025, with full run-rate of 25 million pounds targeted for H2 2025

Arq, Inc. (the "Company" or "Arq"), a producer of activated carbon and other environmentally efficient carbon products for use in purification and sustainable materials, provided an update on the continued execution of its Granular Activated Carbon ("GAC") project.

GAC Production and Ramp-Up Timeline
Arq confirmed that initial production of its proprietary GAC at the Red River facility ("Red River") remains on track to commence in Q1 2025, in line with most recent guidance. Following first production, the Company expects a ramp-up period to reach full production capacity of 25 million pounds annual run-rate of GAC in H2 2025. Once full run-rate capacity is achieved, the Company will have greater visibility on potential additional capacity enhancements.

GAC Customer Engagement & Contract Update
Arq continues to make meaningful progress in commercial discussions for GAC and continues to engage with a range of customers and testing opportunities. As noted on its Q3 2024 earnings call, in addition to PFAS-related customers, discussions with biogas and other industrial customers are advancing positively, with early pricing indications indicating a strong commercial opportunity. Given the need for in-situ pilot testing as a condition to securing long-term contracts from these customers, Arq has elected to strategically hold back additional contract commitments to diversify end-use markets and focus on profitability over volumes. The Company is planning to match its contracting and sales with the production ramp-up timeline in H2 2025.

Capital Expenditures & Cost Management
Arq reported capital expenditures related to its GAC expansion at Red River in Q4 2024 were slightly above expectations, bringing full-year 2024 capex for this project to approximately $80 million. The Company attributes this recent increase to several factors, including the need for additional external professional services, increased small-bore piping needs, and a commitment to maintaining previously communicated timelines. Given knowledge and experience gained from the first phase of construction, the Company does not anticipate similar cost overruns for a second phase of GAC development at the site. Arq continues to evaluate opportunities for additional cost optimization and efficiency gains as the Company scales production.

Commencement of Legal Proceedings
The Company announced today that it had commenced legal proceedings against its design firm for the GAC expansion project at Red River. The Company believes that the design firm was negligent and breached its contract with the Company and as a direct result of this negligence and breach of contract, the Company suffered a material increase in costs and time delays associated with the project versus original forecasts. The Company is seeking damages related to the increased costs and delays it believes resulted from such negligence and contractual breaches. Because of prior actions by the Company to bring certain professional services in-house and to other parties, including those previously disclosed, the Company believes there will be no impact on product performance and as noted above, GAC production is expected to commence in Q1 2025.

Q4 & FY 2024 Earnings Conference Call
Arq will release its Q4 and full-year 2024 financial results on March 5, 2025. The Company will provide separately additional details related to its earnings conference call, as well as its participation in upcoming investor conferences in the near term.


Canada >>  3/21/2025 - PyroGenesis Inc. (“PyroGenesis”), a high-tech company that designs, develops, manufactures and commercializes all-electric plasma processes and sustai...
United Kingdom >>  3/21/2025 - LAYANA Company, a leading IATF 16949-certified total-solution provider for advanced bi-material manufacturing, is announcing significant year-on-year ...

United States >>  3/21/2025 - The California Air Resources Board (CARB) announced the state is moving forward with a groundbreaking effort to reduce planet-warming methane emission...
Austria >>  3/20/2025 - - OMV has successfully started-up its ReOil® plant at OMV’s Schwechat site, boasting a processing capacity of up to 16,000 metric tons of hard-to-recy...

Finland >>  3/20/2025 - In a significant step forward for the carbon removal market, Puro.earth has announced the issuance of over one million tonnes of CO2 Removal Certifica...
Norway >>  3/20/2025 - Methane slip, as based on standard factors, can account for up to 24% of GHG emissions from an LNG-fuelled vessel. As an alternative to using standard...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.