VAALCO Energy, Inc. Updates Gabon Activities

Source: www.gulfoilandgas.com 9/12/2005, Location: Africa

VAALCO Energy, Inc. announced that the Etame consortium has elected to stabilize the production of the Etame Field at between 17,000 and 18,000 barrels of oil per day. The higher initial production levels experienced with the addition of the Etame 6H well resulted in pressure interference with nearby wells and some declines in their productivity. Rather than risk local pressure decline, and possible damage to the reservoir, the Etame ET-3H well will be shut in.

By resetting production the consortium expects improved aquifer support and stable production. The Etame ET-6H well, which has produced at rates in excess of 7,000 barrels oil per day, is the structurally highest well in the field. This well will ultimately recover attic oil that could not have been recovered by any of the other wells in the field.

On the Avouma development project, the Company announced that the fabrication yard building the production platform reopened on Tuesday September 6, 2005 after a ten day shut down for Hurricane Katrina. The Company is assessing additional costs and delays that may occur as a result of other manufacturers of platform equipment that are still shut down. The Company currently believes a delay of between 30 to 90 days for the Avouma project is possible.

VAALCO’s next scheduled lifting for the consortium is set for approximately 600,000 barrels in mid September which will bring total oil sales from Etame to approximately 18 million barrels since inception. The Company expects to report third quarter results during the first week in November.

Formation Evaluation News in Gabon >>

Canada >>  5/28/2020 - Applied Petroleum Technology (APT) has conducted a detailed evaluation of the Southern Grand Banks petroleum system offshore Canada and identified unt...
Indonesia >>  5/26/2020 - Further to the announcement made on 14 April 2020, Coro Energy plc, the Southeast Asian focused upstream oil and gas company, is pleased to announce t...

China >>  5/21/2020 - Empyrean Energy ("Empyrean") is pleased to announce the results of its seismic inversion project, designed to assess the reservoir quality and reservo...
United States >>  5/21/2020 - 88 Energy Limited is pleased to provide the following update related to operations for the recently drilled Charlie-1 appraisal well, located on the N...

Related Categories: Formation Evaluation  General  Geological, Geophysical  Geophysical Contractors  Mud Logging  Reservoir Engineering & Recovery Methods  Seismic survey  Well Completion, Logging, Workover 

Related Articles: Formation Evaluation  General  Geological, Geophysical  Geophysical Contractors  Mud Logging  Reservoir Engineering & Recovery Methods  Seismic survey  Well Completion, Logging, Workover 


Gabon Oil & Gas 1 >>  2 | 3 | 4 |

Oil & Gas Projects in Gabon >>

More News

Related Links

AO BJ BW CD CG CI CM DZ EG ET GA GH GM GN GQ GW KE LR LY MA MG ML MR MZ NA NE NG RW SC SD SL SN SO ST SZ TD TN TZ UG ZA ZM
Gulf Oil and Gas
Copyright © 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.