Canadian Provides Update on Horizon Oil Sands Project

Source: www.gulfoilandgas.com 10/10/2013, Location: North America

Canadian Natural Resources Limited ("Canadian Natural" or the "Company") is pleased to provide an update on its Horizon Oil Sands (“Horizon”) project. Several key milestones were completed at Horizon in Q3/13 as the Company continues to deliver on its strategy to transition to a longer life, low decline asset base which continues to deliver significant and growing free cash flow.

HORIZON EXPANSION
Overall Horizon Phase 2/3 construction, which is targeted to increase production capacity to 250,000 bbl/d of synthetic crude oil (”SCO”), reached approximately 30% physical completion in Q3/13 with current costs continuing to trend slightly below sanctioned cost estimates, as the Company executes a cost driven strategy for expansion.
- The Reliability Phase is approximately 91% physically complete and is trending under its budget of $1.09 billion by approximately 5%. The absorber towers for the Gas Recovery Unit were safely erected and installed in September 2013. The Reliability Phase will increase performance, overall production reliability and recovery of additional light oil barrels with the Gas Recovery Unit as the Company moves into 2014.
o The Reliability Phase provides additional redundancies that facilitate operating the plant more consistently and provides more confidence in reliable production.
- In Q3/13, Phase 2A reached a major milestone with the installation of Coke Drums 33-D-3A/B. The Coke Drums are approximately 9 meters in diameter and stand approximately 43 meters high and were safely lifted and installed in August 2013. Phase 2A is approximately 70% physically complete, on schedule for completion in 2015 and is targeted to add 10,000 bbl/d of additional SCO production capacity at Horizon.
o Completion of Phase 2A will utilize pre-invested infrastructure and equipment to expand the Coker Plant and alleviate the current bottleneck.
- Phase 2B continues to progress on cost and on schedule to add a targeted additional 45,000 bbl/d of SCO in 2016. Currently Phase 2B is approximately 20% physically complete and will increase bitumen yield through the addition of the Vacuum Distillation Unit.
o Phase 2B will expand the capacity of froth treatment, the Gas/Oil hydrotreater and the hydrogen plant. Bids are out for major components on this Phase.
- Phase 3 continues to progress on cost and on schedule to add a targeted additional 80,000 bbl/d of SCO in 2017. Currently Phase 3 is approximately 19% physically complete and will bring Horizon production capacity to 250,000 bbl/d of SCO and will result in additional reliability, redundancy and significant operating cost savings. o Phase 3 will expand capacity through adding extraction trains 3 and 4.

HORIZON OPERATIONS
Operating performance at Horizon has been strong since the Company executed its first major turnaround in May 2013. SCO production for Q3/13 was approximately 111,900 bbl/d, with September 2013 production at approximately 117,200 bbl/d. Canadian Natural expects continued strong production reliability at Horizon with Q4/13 production volumes currently targeted to average between 110,000 bbl/d and 115,000 bbl/d.

Q3/13 OPERATIONAL/FINANCIAL SUMMARY HIGHLIGHTS
Overall Q3/13 was a strong operational quarter for the Company as it achieved record quarterly crude oil production of approximately 508,000 bbl/d and record quarterly BOE production of approximately 701,000 BOE/d. Strong production was driven by operational reliability across all assets. Due to these record production levels and the robust liquids pricing received during Q3/13, cash flow from operations for the quarter will be approximately $2,400 million (approximately $2.21 per common share), which cash flow from operations does not include approximately $170 million of after tax gains realized on certain oil and gas property dispositions completed in Q3/13.



Oil Sands News in Canada >>

United States >>  8/22/2019 - TechnipFMC (FTI) has been awarded a significant integrated Engineering, Procurement, Construction and Installation (iEPCI™) contract by Shell for the ...
United States >>  8/14/2019 - TGS-NOPEC Geophysical Company ASA (TGS) has completed its acquisition of Spectrum ASA (Spectrum), creating a leading global multi-client geophysical d...

United States >>  8/8/2019 - Occidental Petroleum Corporation (OXY) announced the successful completion of its acquisition of Anadarko Petroleum Corporation ("Anadarko") (APC) in ...

Related Categories: Coalbed Methane  General  Heavy Oil  Methane Clathrate  Oil Sands  Oil Shale  Shale Gas  Tight Gas  Tight Oil 

Related Articles: Coalbed Methane  General  Heavy Oil  Methane Clathrate  Oil Sands  Oil Shale  Shale Gas  Tight Gas  Tight Oil 


Canada Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 |

Oil & Gas Projects in Canada >>

More News

Related Links

Gulf Oil and Gas
Copyright © Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.