AWE Limited reports that as at 06:00 hours preparations are being made to drill a second sidetrack on the Pateke-4H development well. Operations have been unable to drill past an obstruction in the lower portion of the first sidetrack (ST-1) and a second sidetrack (ST-2) will be drilled from a measured depth of 3,587m with an 8 1/2 inch drilling assembly.

The forward work plan requires ST-2 to be drilled to a depth of approximately 4,110m and intersect the F10 reservoir at a horizontal angle of approximately 90 degrees. Drilling will continue through the F10 reservoir section to a planned total measured depth of 5,361m, following which a 6 5/8 inch production liner will be installed.

The Kapuni F10 sandstone objective has already been intersected on prognosis with oil shows and real time logging measurements indicating the likely presence of an oil bearing reservoir. The commercial significance of the oil shows will not be clear until the horizontal drilling is completed and the reservoir size and quality is fully assessed.

Based on the additional work required to mitigate the operational difficulties encountered to date, gross pre-completion well costs have increased beyond the pre-spud estimate of USD 55 million (AWE share USD 32 million). An updated estimate of pre-completion well costs will be issued after the horizontal drilling is completed and the production liner has been installed.

The Pateke-4H development well is in PMP 38158 and AWE is the Operator. Located in the offshore Taranaki Basin, New Zealand, PMP 38158 contains the Tui, Amokura and Pateke fields and has been producing since 2007.

Pateke-4H is targeting a mapped northern extension of the currently producing Pateke field. The well is being drilled in water depth of approximately 124m with a planned total measured depth of 5,361m, including a 1,272m horizontal section. If successful, the well will be completed for subsequent tie-back to the Tui FPSO (“Umuroa”) for production in 2015.

The Joint Venture partners in PMP 38158 are:
- AWE Limited (via subsidiaries) (Operator) 57.5%
- New Zealand Oil & Gas (via subsidiaries) 27.5%
- Pan Pacific Petroleum (via subsidiaries) 15.0%


Norway >>  8/12/2022 - Aker BP ASA, operator of production licence 941, has concluded the drilling of wildcat well 6507/3-15.

The well was drilled about 14 km nor...

Norway >>  8/9/2022 - The Petroleum Safety Authority Norway has given Equinor consent for exploration drilling in block 6507/8 in the Norwegian Sea.

Operator: E...


Guyana >>  8/5/2022 - The drilling of the Beebei-Potaro exploratory well, located in the Kanuku licence, off the coast of Guyana, has been finished, according to Tullow Oil...
Australia >>  8/4/2022 - - 21 stages were stimulated, which is the greatest number of stimulation stages in a single well in the Beetaloo to date
- Delivered 927m of st...


Romania >>  8/4/2022 - Serinus Energy plc ("Serinus") (SEN), is pleased to announce that the drilling of the Canar-1 exploration well in Romania commenced.

...

Norway >>  8/3/2022 - The Norwegian Petroleum Directorate (NPD) has granted Equinor a drilling permit for well 6507/8-11 S in production licence PL 124.

Related Categories: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 

Related Articles: Artificial Lift  Cementing, Stimulation  Directional Drilling  Drilling  Drilling Engineering & Equipment Systems  Enhanced Oil Recovery  General  Logging, Perforating, Testing  Offshore Drilling  Reservoir/Completion Consultants  Workover & Well Services  Workover Rigs/Services 


Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.