Gulf Oil and Gas accountACCOUNT

Verenex Provides Libya Operation update

Source: www.gulfoilandgas.com 7/3/2007, Location: Africa

Verenex Energy Inc. provided an update of its operations in Libya. Since the last update on May 16, 2007, the Company's exploration program in Area 47 in Libya has continued to yield excellent results. To date, two wells have been drilled and have tested light sweet crude oil at high rates, athird is testing and a fourth has reached total depth and is logging.

The Company has submitted a preliminary appraisal report to the Libyan National Oil Corporation ("NOC") on its first light sweet crude oil discovery A1-47/02 as required under the Exploration and Production Sharing Agreement("EPSA") for Area 47. The report incorporates results from the drilling, formation evaluation and flow testing programs and makes recommendations on additional seismic reprocessing and interpretation, reservoir analysis andadditional appraisal drilling in areas adjacent to the A1-47/02 structure to determine the size of the discovery and potential recoverable resources.

As announced on April 25, 2007, the A1-47/02 well was flow tested at a maximum combined rate of 12,500 barrels of oil per day (gross) at choke sizes up to 128/64ths inch and 6,586 barrels of oil per day at a restricted choke size of 32/64ths inch, from 174 feet of perforations in three test intervalsin the Lower Acacus Formation. These flow tests confirmed the excellent quality and deliverability of the sandstone reservoirs discovered in the Lower Acacus in this well and provided information to calibrate wireline log andother formation evaluation results.

This combined flow test rate is not necessarily indicative of ultimate production rate in any commercial development which will be determined from reservoir management studies that constitute part of the proposed appraisal program.

The Company has successfully completed flow tests from 312 feet of perforations in five reservoir intervals in the Lower Acacus and Middle Acacus Formations in its second exploration well B1-47/02. The combined measured flow rate of light sweet crude oil exceeds the rate achieved in the Company's firstexploration well A1-47/02 due primarily to the greater perforated pay in the B1-47/02 well.

The Company plans to release details of the flow test results on the B1-47/02 well subject to the approval of the NOC which is currently reviewing the well test results.

The KCA DEUTAG Service Rig 32 was released from the B1-47/02 well on June 5, 2007 and mobilized to the C1-47/02 well to carry out similar flow testing.

The Company has completed flow tests on three intervals in the Lower Acacus Formation at its third exploration well C1-47/02. The results are encouraging, yielding light sweet crude oil at rates that are comparable to the first two wells when normalized to perforated pay thickness.

The Company plans to test up to five reservoir intervals fromapproximately 188 feet of perforations, including four intervals in the Lower Acacus and one interval in the shallower Aouinet Ouenine Formation. This program could extend to mid-July 2007.

At the conclusion of the program, flow test results will be released subject to NOC review and approval.

The Company's fourth exploration well D1-47/02 commenced drilling on May 25, 2007 and reached total depth of 9,720 feet on June 27.

Based on positive mud log results and hydrocarbon shows during drilling, an extensive logging and formation evaluation program is underway similar to the program carried out on the Company's first three exploration wells. This evaluation program could extend to mid-July 2007.

New 3D Seismic Acquisition Program Underway

Survey work has commenced for the Company's planned 2007/2008 3D seismic program along the eastern side of Area 47. The program covers an area of approximately 1,225 square kilometres and encompasses more than 20 prospectsand leads identified from the Company's 2D seismic acquisition program completed in 2006.

The final 3D seismic program design indicates that the acquisition phase could be completed by late December 2007, which is about two to three monthssooner than originally anticipated. Completion of processing and interpretation is targeted for the end of the first quarter of 2008 although the Company anticipates that the initial northern part of the program could be interpreted in the third quarter of 2007 to guide potential drilling in thisarea in late 2007.

Exploration News in Libya >>

Guyana >>  9/16/2019 - Tullow Oil plc (Tullow) announces that the Joe-1 exploration well has successfully opened a new Upper Tertiary oil play in the Guyana basin. ...
Norway >>  9/13/2019 - Norway's Petroleum Safety Authority has given Equinor consent for exploration drilling in Block 7219/9 in the Barents Sea. Well 7219/9-3 is part of pr...

Mexico >>  9/11/2019 - Talos Energy Inc. has received a two-year contract term extension as well as regulatory approvals for additional exploration activities on Block 7, lo...
United Kingdom >>  9/11/2019 - Independent Oil and Gas plc (IOG), the development and production company focused on becoming a substantial UK gas producer, is pleased to provide an ...

Egypt >>  9/8/2019 - President Abdel Fattah El Sisi met with Prime Minister Mostafa Madbouly, Minister of Electricity and Renewable Energy Mohamed Shaker Al Marqabi, Minis...
Nigeria >>  9/6/2019 - LEKOIL, the Africa-focused oil and gas exploration, development and production company, has announced that pursuant to a letter dated 4 September 2019...

Related Categories: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  Food Supplies  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Unskilled Labors  Utility Systems  Waste Disposal  Water Supply Services  Welding Products/Services 

Related Articles: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Transportation, 4X4 Trucks  Utility Systems  Water Supply Services  Welding Products/Services 


Libya Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |

Oil & Gas Projects in Libya >>

More News

Related Links

AO BJ BW CD CG CI CM DZ EG ET GA GH GM GN GQ GW KE LR LY MA MG ML MR MZ NA NE NG RW SC SD SL SN SO ST SZ TD TN TZ UG ZA ZM
Gulf Oil and Gas