Candax Energy Announces El Bibane Production Start Up

Source: www.gulfoilandgas.com 3/25/2008, Location: Africa

Candax Energy announced the commencement of production from the El Bibane Field offshore Tunisia. During the week of March 3rd the EBB-5 well was tested and flowed gas and condensate to the onshore Central Processing Facility (CPF) to clean up the well and enable the onshore plant commissioning to be initiated.

The EBB-4 well successfully commenced oil production during the week of March 16th. Oil production rates have been variable due to onshore plant commissioning and weather related delays to the offshore tie-in activities, both of which have necessitated several shut-downs. The peak daily production rate thus far is approximately 1,400 bpd of oil and Candax expects oil production levels to rise considerably over the coming weeks as production from EBB-4 is optimized and the EBB-3 well is tied in and brought on stream. Candax plans to release further production updates once these operations have been completed.

The final well in the El Bibane re-development project, EBB-3, was completed on March 18th and the "West Titania" rig move has been initiated for demobilisation to Malta. The installation of the EBB-3 platform and pipeline hook-ups with the other wells is ongoing. The SEEB power station is also being commissioned and will be ready to commence power generation operations once gas production has been stabilized in April.

Michael Wood, President and Chief Executive Officer, commented: "We are pleased to have completed the three well drilling program at El Bibane and are encouraged by the initial oil production rates from the EBB-4 well. We are focusing our efforts on completing the EBB-3 platform installation, pipeline hookups and commissioning to optimize the oil production capability of the field in the coming weeks."

Exploration News in Tunisia >>

Indonesia >>  2/19/2019 - Repsol and partners PETRONAS and MOECO have made the largest gas find in Indonesia in 18 years. The discovery is also among the ten largest finds worl...
Norway >>  2/18/2019 - Wintershall Norge A/S, operator of production licence 847, has concluded the drilling of wildcat well 6706/6-2 S. The well was drilled about 60 kilom...

United States >>  2/18/2019 - 88 Energy has advised that the Winx-1 well, North Slope of Alaska, spudded on schedule on Feb 15 (AK time). The well was drilled to 600 ft prior to pu...
Norway >>  2/15/2019 - Equinor Energy AS, operator of production licence 248 C, has completed the drilling of wildcat well 35/11-22 S. The well was drilled in the northern ...

Norway >>  2/15/2019 - Wellesley Petroleum AS, operator of production licence 931, has completed the drilling of wildcat well 35/4-2. The well was drilled about 33 kilometr...
United States >>  2/15/2019 - 88 Energy has advised the following in relation to its oil and gas operations on the North Slope of Alaska. ...

Related Categories: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  Food Supplies  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Unskilled Labors  Utility Systems  Waste Disposal  Water Supply Services  Welding Products/Services 

Related Articles: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Transportation, 4X4 Trucks  Utility Systems  Water Supply Services  Welding Products/Services 


Tunisia Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 |

Oil & Gas Projects in Tunisia >>

More News

Related Links

AO BJ BW CD CG CI CM DZ EG ET GA GH GM GN GQ GW KE LR LY MA MG ML MR MZ NA NE NG RW SC SD SL SN SO ST SZ TD TN TZ UG ZA ZM
Gulf Oil and Gas
Copyright Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.