BP Sends Second Shah Deniz 2 Platform Jacket Offshore

Source: www.gulfoilandgas.com 3/16/2017, Location: Asia

The Shah Deniz consortium has announced the sail away of the second jacket for the Shah Deniz Stage 2 platforms. The Quarters and Utilities (QU) platform jacket sailed away to the Shah Deniz contract area in the Caspian Sea from the Heydar Aliyev Baku Deepwater Jackets Factory (BDJF) ahead of schedule on 15 March.

The transportation, launch, positioning, pile installation and final completion activities of the jacket structure are expected to take around 75 days, depending on the prevailing weather conditions.

The construction of the jacket was completed ahead of schedule on 20 February 2017 and was then successfully loaded onto the transportation barge STB-1 at the quayside of BDJF.

The QU platform jacket, built by the BOS Shelf, Star Gulf and Saipem consortium, was fully constructed in country at the BDJF, using local construction infrastructure and facilities. 2000 people including sub-contractors and specialist vendors were involved in the construction works. Some 90% of the construction workforce was Azerbaijani citizens.

Ewan Drummond, Vice-President, Shah Deniz 2 Projects, said: 'The second jacket sail away is the first major milestone planned for this year and we are pleased to have achieved it ahead of schedule. 2017 is an important year for BP and for the Shah Deniz 2 project, which is already around 90% complete. We have planned a series of key completion milestones for this year. We are committed to achieving all of these milestones on schedule to make BPs 25th anniversary celebrations in Azerbaijan a big success.

'On this occasion, I would like to thank SOCAR and our partners for their support and cooperation in moving this giant project forward. My thanks are also to all people representing BP, contractors and subcontractors whose hard work has made it possible to achieve this milestone ahead of schedule. I would like to specifically thank the BOS Shelf, Star Gulf and Saipem consortium for their firm commitment to BPs safety standards throughout the 22-month construction period of this jacket. This is a great safety achievement and I am confident that the offshore installation will be performed with the same level of commitment to safety and quality'.

The QU platform jacket weighs approx. 12,084 tonnes and stands 105 metres high. It contains 31 J Tubes, 7 utility caissons and 3 J tube caissons. The jacket will be installed in a water depth of 95 metres.


Norway >>  6/15/2021 - Wood has been awarded an extension to its existing framework agreement with international energy company, Equinor, to support their offshore assets in...
Scotland >>  6/15/2021 - Optimizing waste streams throughout the decommissioning process, the strategy promises to minimize required Intermediate Level Waste and associated co...

Norway >>  6/10/2021 - Neptune Energy announced the successful completion of a virtual reality pilot on its operated Gjoa platform in the Norwegian North Sea, enabling teams...
United Kingdom >>  6/10/2021 - Solstad Offshore ASA is pleased to announce that the company has signed long -term contracts with Harbour Energy for two large PSVs. Normand Service ...

United Kingdom >>  6/9/2021 - Pioneering Spirit today successfully executed the single-lift removal of the former DP3 gas production topsides from Spirit Energys Morecambe Bay de...
Norway >>  6/8/2021 - Aker Solutions has delivered yet another steel substructure for the largest industry project ever in Norway, the Johan Sverdrup field.

Prev...


Related Categories: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 

Related Articles: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 


Gulf Oil and Gas
Copyright 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.