13As Replacement Jacket Hit 65% of Progress

Source: www.gulfoilandgas.com 7/1/2017, Location: Asia

The development plan director of phase 13 announced 65 percent of progress for 13As replacement jacket, he said that this structure will be transferring to install on platform 13A' location this July.

Referring to the incident caused by the crash of Norwegian tanker with the platform's leg in SPD13A on April 2015, PayamMotamed stated "the security operations of well no.5 was successfully completed at that time by performing one of the most complex sea operations in a very hard condition and at the depth of 40 meters from sea level.

Subsequently the debris operation was started under the supervision of InsurerCompany that has hit 95 percent progress so far".public relations reported.

He added that given the incident before the delivery of the structure and its wells to the National Iranian Oil Company (NIOC), all responsibilities for the process of obtaining damages, legal and contractual issues from the consortium of development plan of phase 13 is borne by the contractor and Insurer Company under the contract with the Norwegian tanker. Thus, a new jacket is being constructed by an Italian company and its main components are being assembled in the yard of UAE as requested byInsurerCompany. Pars Oil and Gas Company (POGC) has no responsibility in this regard.

Motamedpointed out that Insurer is obliged to repair damaged installations in accordance with pre-incidental conditions and also is free to refer to foreign and domestic contractors.

The official said that based on schedule and intensive planning, this structure has reached to 65 percent of progress at this time and will be transferred to install on 13As location this July.

Offshore Platforms News in Iran >>

Norway >>  1/16/2019 - Aker BP became the first company on the Norwegian Continental Shelf to operate a staffed platform from an onshore control room. Ivar Aasen in the Nort...
Iran >>  1/12/2019 - The first platform belonging to the phases22-24 started up with the capacity of 500 million cubic feet a day. In order to supply the gas required for ...

Iran >>  1/7/2019 - The second deck belonging to phases22-24 was loaded out and now is ready to sail out. The first satellite deck for phases22-24 which is called 24A, we...
United Arab Emirates >>  12/27/2018 - Drydocks World, a leading marine, onshore and offshore service provider to the shipping, oil, gas and renewable energy sectors, has completed the Rash...

United Kingdom >>  12/26/2018 - When the Ninian Central oil production platform was towed out of Loch Kishorn in May 1978, at just over 600,000 tonnes it was the largest concrete str...
Azerbaijan >>  12/24/2018 - A new stationary drilling platform built by SOCAR Oil and Gas Construction Trust at the Bulla-Deniz field was commissioned in a ceremony attended by R...

Related Categories: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 

Related Articles: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 


Iran Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |

Oil & Gas Projects in Iran >>

More News

Related Links

Gulf Oil and Gas
Copyright Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.