Trans Adriatic Pipeline is 50% Completed

Source: www.gulfoilandgas.com 9/7/2017, Location: Asia

The Trans Adriatic Pipeline (TAP) is now more than 50% completed, nearly 16 months after construction began. This includes all engineering, procurement and construction scope. As of early-September 2017:

TAP remains on its journey to deliver world-class health and safety performance across Greece, Albania and Italy. To date, our teams have collectively worked over 16 million manhours and driven approximately 43 million kilometres without a major incident.

TAP’s contractors have cleared approx. 70% of the project route in Greece and Albania (539km out of 765km). Also, over 45% of welded steel pipes are already in the ground (backfilled).

Approximately 95% of the total 55,000 pipes to be used for the construction of the pipeline have been received in Greece, Albania and Italy. The last shipment of offshore line pipes has been offloaded in Brindisi, Italy, between 3 and 6 September 2017.

More than 5,500 people have been working for the project across TAP’s host countries - over 85% of which have been staff employed locally.

TAP has implemented a wide range of social and environmental investment (SEI) programmes in the communities along its route. Substantial projects are due to be rolled out in the upcoming months. In total, TAP will invest over €55 million in SEI in Greece, Albania and Italy.

TAP Managing Director Luca Schieppati said: “We are pleased that TAP continues to progress on time and on budget. We therefore remain on track to deliver the first Shah Deniz II gas in 2020, bringing a much-needed new source of energy into the European energy network.”

“I want to underline that our project is built with the utmost care for the environment. Our teams are working very carefully along our route to ensure that the land on which construction has been completed is returned to the owners or users in its original condition or better. We are also collaborating with local authorities and local stakeholders to ensure that the benefits of our project are tangible across all those communities crossed by the pipeline.” Schieppati added.

Oil and Gas Pipeline >>

Oil and Gas Pipeline News in Azerbaijan >>

Canada >>  1/20/2021 - TC Energy Corporation announced it is disappointed with the expected action to revoke the existing Presidential Permit for the Keystone XL pipeline. T...
Russia >>  1/14/2021 - In 2020, Transneft Siberia fully implemented the technical upgrading and revamping programme for the oil trunk pipelines’ (OTPs) and oil pumping stati...

Peru >>  1/12/2021 - PetroTal Corp. has mandated Pareto Securities AS to arrange a series of fixed income investor virtual meetings commencing January 14, 2021. ...
Georgia >>  1/11/2021 - Block Energy plc, the development and production company focused on Georgia, is pleased to provide an update regarding gas sales at its West Rustavi f...

Kazakhstan >>  1/11/2021 - In 2020, 59,027,273 gross tons of crude oil were lifted from CPC Marine Terminal. March when 6,45I0,676 tons were loaded on vessels became the top mon...
United States >>  1/4/2021 - Kinder Morgan, Inc. (KMI) announced that the Permian Highway Pipeline (PHP) began full commercial in-service on January 1, 2021. The pipeline has been...

Related Categories: General  LNG Carriers  LNG Terminal  Natural Gas Storage  Oil and Gas Pipeline  Oil Storage  Railways  Tank Truck  Tankers 

Related Articles: General  LNG Carriers  LNG Terminal  Natural Gas Storage  Oil and Gas Pipeline  Oil Storage  Railways  Tank Truck  Tankers 


Azerbaijan Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |

Oil & Gas Projects in Azerbaijan >>

More News

Related Links

Gulf Oil and Gas
Copyright © 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.