Acting within the framework of the Concept of RPM (reservoir pressure maintenance) System Development for the 2016-2020 TATNEFT Company continued the introduction of advanced technologies to maintain the reservoir pressure, aimed at reducing energy costs and improving the production efficiency.
In 2017, the plan for the commissioning of new injection wells for the Company was fulfilled by 105.5 percent: with the plan 145 there were 153 wells were put into operation.
DCI technologies (dual completion and injection) were implemented in 67 injection wells. At present, this technology is applied in 795 wells.
The Company continued the work aimed at protecting the well downhole equipment against high pressure and corrosion. High pressure leak-proof packers were installed in 340 injection wells. Currently, the number of the injection wells where the mentioned packers have been installed totals 7,623 wells accounting for 77.6 percent of the Company’s operating injection wells stock.
There were fiberglass pipes actively introduced at TATNEFT in 2017 as the supply pipelines, which increased the reliability of water lines, while optimizing construction and capital repair costs. 23.5 km of water pipelines were built during the reporting period.
In the course of implementing programs aimed at optimization of energy consumption in the RPM system and import substitution in 2017 there were18 domestic positive displacement pumping systems introduced, which allowed reducing the specific energy consumption for injecting water to maintain the reservoir pressure to 6.76 kW*h / m3.
The work was also continued to provide fresh water for boilers at the HVO deposits for steam generation, injection of associated water and wastewater from boilers, commissioning of (associated water treatment station) Kamenka and UPPDV Karmalka.