SP Developing Platforms to be Installed Based on Drilling Completion Schedule

Source: www.gulfoilandgas.com 5/31/2018, Location: Asia

Based on planning and prioritization, 6 out of 9 developing platforms will be installed and launched by the end of Iranian calendar year.

Pointing to 85-95 percent of progress made in developing platforms, project planning and control director Ali Afarideh Ghiasi announced that 6 out of 9 platforms, based on planning and prioritization, will be installed and launched by the end of Iranian calendar year (March 20, 2019).

Ali Afarideh mentioned the balanced trend of work progress in constructing south pars remaining platforms, in parallel with drilling and completion of developmental wells related to each platform are among the most important prioritization factors to carry and install. Accordingly, the first priority for the employer to carry and install these platforms is on the basis of the possibility to produce more gas by such platforms from the common field.

Having the platform 22 installed last week, platform 13B, 14C, and 24A will be loaded out by the end of summer and the others namely 23, 24B, 13A, 13C, 14D will continue to be available.

Recalling the platform 14A installation in ISOICO yard, Afarideh added up the 2nd platform, namely 14B is now under construction in the same yard and will be ready to get installed by the end of coming March.

As a result of follow-up and continuous monitoring in executive process, appropriate progresses had been made in onshore refineries last year despite all the existing restrictions. Currently, the 1st and 2nd sweetening row of phase 13 along with the 1st row of the phases 22-24 have been launched and the others will be exploited in coming months.

Offshore Platforms News in Iran >>

Norway >>  1/16/2019 - Aker BP became the first company on the Norwegian Continental Shelf to operate a staffed platform from an onshore control room. Ivar Aasen in the Nort...
Iran >>  1/12/2019 - The first platform belonging to the phases22-24 started up with the capacity of 500 million cubic feet a day. In order to supply the gas required for ...

Iran >>  1/7/2019 - The second deck belonging to phases22-24 was loaded out and now is ready to sail out. The first satellite deck for phases22-24 which is called 24A, we...
United Arab Emirates >>  12/27/2018 - Drydocks World, a leading marine, onshore and offshore service provider to the shipping, oil, gas and renewable energy sectors, has completed the Rash...

United Kingdom >>  12/26/2018 - When the Ninian Central oil production platform was towed out of Loch Kishorn in May 1978, at just over 600,000 tonnes it was the largest concrete str...
Azerbaijan >>  12/24/2018 - A new stationary drilling platform built by SOCAR Oil and Gas Construction Trust at the Bulla-Deniz field was commissioned in a ceremony attended by R...

Related Categories: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 

Related Articles: Diving Contractors  Dredging  FPSO Vessels and Equipment  General  Marine Services  Mooring Systems  Offshore Platforms  Subsea Production 


Iran Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |

More News

Related Links

Gulf Oil and Gas
Copyright Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.