Nord Stream AG has completed all planned maintenance works on the twin gas pipelines timely and in full. Between 16 July and 27 July 2019, all planned maintenance works on mechanical components, as well as testing of the automation system were carried out. After the temporary shutdown of the pipeline system, gas transmission resumed today and the full capacity of the pipeline is now available again to continue to fulfil all nominations.

Nord Stream AG’s Maintenance Director Olivier Escola summarises the shutdown: “We have successfully completed the annual maintenance works of the Nord Stream Pipeline on 27 July 2019. Our Operations and Maintenance teams as well as external contractors planned the shutdown thoroughly to ensure the safe and timely inspection of the pipeline system. The annual maintenance shutdown is a major part of our long-term Pipeline Integrity Management Strategy to ensure safe and reliable delivery of natural gas to the EU.”

The schedule for these maintenance activities has been closely coordinated with Nord Stream’s upstream and downstream partners well in advance. The temporary shutdown of the pipeline has been factored into the nominations of gas to be transported via Nord Stream to downstream European partners.

Maintenance and Repair News in Russia >>

Qatar >>  10/10/2019 - International specialist equipment and integrated engineering services company, Sparrows Group, has been awarded its first contract with Qatar Petrole...
Australia >>  10/7/2019 - SNC-Lavalin (SNC) has been awarded a three-year provision of operations and maintenance workforce contract from Shell Australia for its QGC upstream a...

Libya >>  10/6/2019 - The National Oil Corporation (NOC) will close the gas plant at the port of Zueitina for scheduled maintenance from October 7-14, 2019. Production...
Norway >>  9/24/2019 - Archer Limited (“Archer”) announces that Archer AS has been awarded a 15 month extension to Archer’s existing platform drilling and maintenance servic...

Related Categories: Consultancy  Engineering  FEED  General  Maintenance and Repair  Process Technology Licensing  Production Engineering  Project & Resource Management 

Related Articles: Consultancy  Engineering  FEED  General  Maintenance and Repair  Process Technology Licensing  Production Engineering  Project & Resource Management 


Russia Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 |

Oil & Gas Projects in Russia >>

More News

Related Links

Gulf Oil and Gas
Copyright © 2019 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.