The pipelay vessel CASTORO 10 (C10) is currently located off Rügen to tie together the two ends of a Nord Stream 2 pipe string laid last year on the seabed. The two sections will be connected above water with a weld seam.

In what is known as an Above-Water Tie-In (AWTI) both pipe ends will be lifted out of the water and then cut, aligned and welded together from a working platform attached to the C10. The weld seam is ultrasonically tested and coated with an anti-corrosion protection. Afterwards, the pipe string will be placed on the Baltic seafloor in a slight arc.

Including all preparation and follow-up work, the procedure takes two to three weeks. With optimal weather conditions and smooth operations, the works above water can be completed within just a week.

For the duration of the works we kindly ask all mariners in the area for increased attention in the interest of their safety. The C10 is situated northwest of the “Landtief” approach and positioned with eight anchors. Due to the anchor pattern as well as diving works, a safety distance of at least 1,000 metres from C10 must be observed (see also: BfS (T)105/19).

Work on the Nord Stream 2 Pipeline continues to proceed as scheduled. Altogether more than 1,700 kilometres (over 70 percent) of both pipe strings have been laid in accordance with the existing permits in the waters of Germany, Sweden, Finland and Russia.

Oil and Gas Pipeline >>

Oil and Gas Pipeline News in Russia >>

Russia >>  11/8/2019 - A working meeting between Alexey Miller, Chairman of the Gazprom Management Committee, and Andreas Schierenbeck, Chairman of the Management Board of U...
Russia >>  11/1/2019 - The leading global quality assurance and risk management company DNV GL has extended the certificate of conformity to the offshore standard for underw...

Denmark >>  10/30/2019 - Nord Stream 2 has obtained the permit to construct its planned pipeline system in the Danish Exclusive Economic Zone (EEZ) south-east of Bornholm. The...
Russia >>  10/30/2019 - President of LUKOIL Vagit Alekperov and General Director of Hungarian oil and gas company MOL Zsolt Hern?di have signed a Memorandum of Understanding ...

Related Categories: General  LNG Carriers  LNG Terminal  Natural Gas Storage  Oil and Gas Pipeline  Oil Storage  Railways  Tank Truck  Tankers 

Related Articles: General  LNG Carriers  LNG Terminal  Natural Gas Storage  Oil and Gas Pipeline  Oil Storage  Railways  Tank Truck  Tankers 


Russia Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 |

Oil & Gas Projects in Russia >>

More News

Related Links

Gulf Oil and Gas
Copyright © 2019 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.