Zennor Announces Completion of 2019 Finlaggan Subsea Installation Campaign

Source: www.gulfoilandgas.com 10/1/2019, Location: Europe

Zennor Petroleum Limited (Zennor), through its subsidiary Zennor Pathway Limited, is currently developing the 100% owned Finlaggan field in the UK Central North Sea (block 21/05c and 21/05d, Licence P2013). The development project is targeting 30mmboe of gas condensate reserves from two subsea production wells tied back 20km to the Britannia platform.

Subsea Facilities Update
Zennor is pleased to announce that the 2019 Finlaggan subsea installation campaign utilising six separate vessels over the summer has been safely and successfully completed.

The programme has seen the 20km long, 10” insulated (pipe-in-pipe) Finlaggan pipeline laid and trenched. After the flushing and pigging of the pipeline the 20km long infield umbilical was laid in the open trench adjacent to the pipeline.

Rock dumping of the pipeline and umbilical was completed this weekend with the rock-dumping vessel the last to leave the field.

Critical work inside the Britannia 500 metre zone was also completed with the installation of the subsea isolation valve (“SSIV”) structure and the pull-in of the SSIV umbilical to the Britannia platform.

At year-end the Finlaggan project will be approaching 85% completion on a value of work done basis.

As previously reported, both Finlaggan production wells (F1 and F2) have already been drilled and tested, with each well flowing at more than 12,000 boepd at significantly higher than expected flowing wellhead pressures.

The remaining subsea scope, which includes the installation of a manifold at the Finlaggan location, will take place following the planned triennial Britannia/FPS shut down in 2020.

The Finlaggan development project remains on schedule for first production in Q4 2020 as planned.

Portfolio Update
Zennor has been progressing its operated Greenwell and Leverett projects in Block 15/29c and Blocks 21/2d and 21/3d respectively.

On Greenwell, Zennor is evaluating bids for wellheads and site surveys that will enable a pilot well to be drilled in 2020 to facilitate a future fast-track development. In parallel, technical discussions continue with Block 21/03a licensees over plans for the Leverett discovery. Both Greenwell and Leverett are potential tiebacks to the existing Britannia Area infrastructure, with first production targeted for 2022 and 2023 respectively.

Elsewhere, rapid progress is also being made on Zennor’s non-operated Platypus and Skua development projects, with both expected to reach project sanction in 2020.

Martin Rowe, Zennor’s Managing Director, said: “The completion of this 2019 subsea construction campaign is a significant step forward in the Finlaggan project. The success of the campaign is very clearly attributed to the time and effort invested in the planning and preparation phases, the professionalism of the offshore teams and the close working relationships between the Britannia operator, installation contractor and Zennor teams. Finlaggan remains on track for first production in Q4 2020, taking our production towards 25,000 boepd in the near term.

Across the wider portfolio, our fully-funded development programme will see us reach production between 30,000 – 35,000 boepd by 2023.”

Development News in United Kingdom >>

Libya >>  12/10/2019 - Total and National Oil Corporation (NOC), with the agreement of the Government of Libya, signed an agreement to implement Total’s participation in the...
Poland >>  12/5/2019 - Ansila Energy has announced the results of a Conceptual Field Development Plan (CFDP) for the Gora license and economic evaluation of the unconvention...

Australia >>  12/4/2019 - Strike Energy Limited has announced that, following its successful capital procurement program, the Company is fully funded to deliver its planned exp...
Australia >>  12/3/2019 - Carnarvon Petroleum Limited advises that the Operator of the Dorado Project, Santos Limited has released initial ‘concept select’ information with res...

Senegal >>  12/3/2019 - FAR Limited, as part of the Rufisque Sangomar and Sangomar Deep (RSSD) joint venture advises that the final Sangomar Field Development and Exploitatio...
Iran >>  11/26/2019 - The operator of phase 14 development project of the South Pars gas field said the offshore section of the project would be complete by December. ...

Related Categories: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  Food Supplies  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Unskilled Labors  Utility Systems  Waste Disposal  Water Supply Services  Welding Products/Services 

Related Articles: Camp Building  Cleaning Equipment, Services  Communication  Corrosion Products/Services  Development  Exploration  General  Labor Services  Land & Leasing  Mine Clearance  Oil & Gas Companies  Production  Service Companies  Skilled Labors  Transportation, 4X4 Trucks  Utility Systems  Water Supply Services  Welding Products/Services 


United Kingdom Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 |

More News

Related Links

Gulf Oil and Gas
Copyright © 2019 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.