Cooper Energy announces the Sole Gas Project has passed a critical milestone with the entry of gas from the Eastern Gas Pipeline into the Orbost Gas Processing Plant.

The Orbost Gas Processing Plant is being upgraded by APA Group (APA) to process gas from the Sole gas field. As previously advised, the development and commissioning of Sole has been completed and the field is ready to supply gas.

Commissioning of the Orbost plant is proceeding towards its second phase, which will include introduction of gas from Sole and commissioning of raw gas processing facilities. Completion of second phase commissioning is to be followed by a plant production test and the commencement of firm gas supply from Sole.

First gas flow from the field to the plant is anticipated later in February. Full rate production and commercial operation for firm gas supply are anticipated in March 2020.


Related Categories: Deodorization system  Gas dehydration  Gas sweetening  Gas Treating  General  GTL Processing  LNG Processing  LPG Domestic use  LPG Odorless  Packing  Phase Separation  Scrubbers 

Related Articles: Gas dehydration  Gas sweetening  Gas Treating  General  GTL Processing  LNG Processing  LPG Domestic use  LPG Odorless  Packing  Phase Separation  Scrubbers 


Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.