Dorado Field Development Update

Source: www.gulfoilandgas.com 5/13/2020, Location: Not categorized

Carnarvon Petroleum Limited advises that important progress has been made with the Dorado field development in relation to advancing work on the Floating Production Storage and Offtake (“FPSO”) vessel and the well head platform (“WHP”). Pre-Front End Engineering Design (“pre-FEED”) contracts were recently awarded to three leading contractors.

Under the terms of the contracts the parties will work independently to advance their FPSO designs and mature their vessel construction plans and supply terms. The award of these contracts enables the Joint Venture to maintain its project schedule.

One of the pre-FEED contractors will be selected at the end of the pre-FEED stage to commence the formal FEED work. The award of the FEED contract is expected to occur later this calendar year. The pre-FEED process will also determine the contracting strategy for the FPSO.

By appointing three contractors to separately undertake this engineering and design work, the Joint Venture will be able to consider the optimal technical design, cost and schedule for the provision of the FPSO.

Expressions of Interest (“EOI”) have now been received from a significant number of companies for the fixed well head platform (“WHP”) that will support the production and ancillary wells and connect to and supply the FPSO. A short list of contractors will shortly be invited to tender for all or relevant parts of the WHP work including engineering and design, fabrication of jacket and topsides, and transport & installation into the field. Additional work for this project, including the preparation of the Field Development Plan and Offshore Project Plan, are also progressing on schedule.

As outlined in previous updates, the FEED process for the Dorado field development is a relatively low cost phase within the total field development. The Joint Venture intends to progress this phase broadly as scheduled (subject to operational impacts associated with COVID-19 restrictions). The current schedule has the Final Investment Decision (“FID”) slated for 2021, however this will be subject to market conditions at the relevant time.

Carnarvon’s Managing Director, Adrian Cook said:
“The award of the pre-FEED contracts for the supply of an FPSO is a significant step and demonstrates the momentum which is building within the Dorado development project. This is testament to the quality of the project as we have the confidence to enter the next phase of development during this short period of uncertainty.


Italy >>  10/7/2021 - Jan De Nul Group has selected Remazel S.p.A. for the delivery of a set of cradles, a skidding system and an upending hinge for its new Floating Instal...
Brazil >>  10/6/2021 - The first oil transfer operation from the FPSO Carioca - the first definitive production system installed in the Sepia field, in the Santos Basin pre-...

United Arab Emirates >>  10/5/2021 - First steel has been cut as part of the latest ship repair and conversion project at Drydocks World.
Drydocks World Dubai, part of DP World, ha...

Australia >>  9/24/2021 - BW Offshore is pleased to announce that the regulatory approval has now been granted for the Joint Venture Partnership consisting of BW Offshore Limit...

Bermuda >>  9/24/2021 - Hoegh LNG Holdings Ltd. announces that Hoegh LNG Partners LP has issued a press release related to a new long-term FSRU contract for Hoegh Gallant for...
Brazil >>  9/23/2021 - SBM Offshore is pleased to announce that it has secured a US$635 million bridge loan facility for the financing of the construction of FPSO Almirante ...




Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.