Transneft Completes Construction of Tank at LODS in Ulyanovsk Region

Source: www.gulfoilandgas.com 7/17/2020, Location: Asia

A new tank with a volume of 50,000 m3 was commissioned at the Klin line operation dispatcher station of the Penza Regional Directorate of Transneft Druzhba.

The construction of the vertical floating-roof tank (VFRT) was launched in September 2018 as part of the technical upgrading, revamping and overhaul programme of the company to replace the decommissioned tank of the same volume.

The specialists installed automation, grounding, fire extinguishing, irrigation and electrochemical protection systems.

Also installed were process pipelines. Power supply networks and a production waste and storm water sewage system were laid. Gate valves, lightning rods and searchlight towers were installed.

Vessels, Tanks >>

Vessels, Tanks News in Russia >>

Singapore >>  10/9/2020 - Keppel Offshore & Marine Ltd (Keppel O&M) has secured a contract valued at approximately S$600m from an energy company for the engineering, procuremen...
Indonesia >>  9/28/2020 - Honeywell announced PT Pertamina (Persero) will use Honeywell UOP technologies to produce advanced biofuels at its Plaju and Cilacap refineries in Ind...




Russia Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 |

More News

Related Links

Gulf Oil and Gas
Copyright 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.