Regulatory Approvals Completed for Ironbark-1 Well

Source: www.gulfoilandgas.com 9/22/2020, Location: Not categorized

- Regulatory approvals for the Ironbark-1 well have been completed
- Drilling is expected to commence late October 2020

Cue Energy reports that regulatory approvals required for the drilling of the Ironbark-1 well in exploration permit WA-359-P have now been completed and the Operator, BP, is making final preparations for the handover of the Ocean Apex drilling rig, expected to be in October.

The Well Operations Management Plan and the Safety Case for the Ocean Apex drilling rig were the final regulatory documents required to be approved by the National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA). Both of these documents have now been approved.

Mobilisation of the Ocean Apex drilling rig for the Ironbark-1 well is expected to commence mid-October, with drilling expected to begin by the end of October.

Exploration permit WA-359-P is located in the Carnarvon Basin, offshore Western Australia, approx. 50km from existing North West Shelf LNG infrastructure. The Ironbark-1 well is expected to drill to approx. 5500 metres and will be the first test of the world class Ironbark gas prospect.

Cue is fully funded for its expected participating interest costs of the well through funding from farm-in agreements with partners BP, Beach Energy and New Zealand Oil & Gas and approx. US$8 million of cash reserves which have been escrowed.

The WA-359-P Joint Venture participating interests are: BP (operator) 42.5%; Cue 21.5%; Beach Energy 21%; New Zealand Oil & Gas 15%.


Cuba >>  5/23/2022 - Melbana Energy Limited is pleased to provide this update on its two well exploration drilling program in its Block 9 contract area, onshore Cuba (Melb...
Norway >>  5/23/2022 - The Norwegian Petroleum Directorate (NPD) has granted Aker BP ASA drilling permit for well 6507/3-15 and well 6507/3-16, cf. Section 13 of the Resourc...

Norway >>  5/23/2022 - The Norwegian Petroleum Directorate (NPD) has granted Equinor Energy AS drilling permit for well 30/3-11 S, cf. Section 13 of the Resource Management ...
Canada >>  5/19/2022 - PetroTal Corp. is pleased to announce that Q1 2022 results will be released on May 26, 2022, along with an extended investor webcast. Additionally, th...

Egypt >>  5/18/2022 - SDX Energy Plc (SDX) is pleased to announce the spudding of the MSD-24 infill development well on the Meseda field. This well is the fourth in a fully...
Australia >>  5/16/2022 - Highlights
- Drilling of Glenaras 28 complete
- Well encountered 27m of gassy coals
- Steps underway to mitigate impact of further uns...





Gulf Oil and Gas
Copyright 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.