Warrego & Strike Align for Joint Development

Source: www.gulfoilandgas.com 10/8/2020, Location: Not categorized

Warrego Energy Limited has executed a binding Heads of Agreement (HOA) with joint venture partner Strike Energy Limited to ensure both parties are aligned on the development of the West Erregulla gas field in EP469, onshore Perth Basin, Western Australia.

The HOA provides an agreed pathway for the Phase 1 development of West Erregulla including:
• Gas processing and plant capacity;
• Gas balancing and gas sales; and
• Optimisation of timing and alignment of critical activities including a Final Investment Decision (FID) and the current appraisal drilling campaign.

Phase 1 development of West Erregulla is subject to FID being taken by the parties by the end of Q1 CY2021, completion of definitive documentation for the gas processing arrangements, and completion of limited due diligence.

Upstream Development
On the back of substantial foundation gas sales by both parties1, the joint venture has agreed a significant increase in Phase 1 capacity to 80 TJ/d delivered to the Dampier to Bunbury Natural Gas Pipeline (DBNGP). The Australian Gas Infrastructure Group (AGIG) remains the preferred proponent to build, own and operate the facility and will complete a supplementary FEED study for the larger capacity plant by the end of CY2020.

The joint venture partners plan to seek financing for the construction of the Phase 1 development on a co-ordinated basis. The partners expect to generate superior outcomes by following this process. The joint venture is expected to be in a position to consider FID by the end of Q1 CY2021 following the drilling, testing and evaluation of the WE-3 and possibly WE-4 appraisal wells. The target date for first gas sales from West Erregulla remains mid-2022. The joint venture has also approved the addition of WE-5 to the current drilling campaign, but this well is unlikely to be drilled before FID is taken.

West Erregulla Gas Sales
Warrego and Strike have entered into a gas balancing arrangement to align the interests of both parties with respect to the difference in total contracted volumes and contract commencement dates for each foundation gas sales agreement. This will ensure the seamless delivery of sales gas to foundation gas customers and enable the joint venture partners to sell uncontracted gas on an equal basis.


Australia >>  8/17/2022 - The following update on the Dorado development inside Production License WA-64-L and the Pavo pre-development studies within Exploration Permit WA-438...
China >>  8/17/2022 - On August 15, in Erlian Menglin Oilfield, Huabei Oilfield, 20 days after the "ignition" of three gas injection wells, the gas injection pressure, temp...

Norway >>  8/10/2022 - Aker BP (operator) and licence partners Petoro and LOTOS Exploration & Production Norge submitted a plan for development and operation (PDO) for Trell...
Denmark >>  8/3/2022 - Norwegian Energy Company ASA (“Noreco” or the “Company”) has today published an update on the Tyra Redevelopment Project (“Tyra II” or the “Project”) ...

Nigeria >>  8/3/2022 - Sirius, an African focused oil & gas production and development company, is pleased to announce that its JV partner, COPDC, has received the requisite...
United Kingdom >>  7/31/2022 - Ping Petroleum UK has reaffirmed its commitment to develop the Avalon Field, in the Central North Sea, with rejuvenation plans for the Hummingbird FPS...




Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.