Gulf Oil and Gas accountACCOUNT

Long Term Outage for Hammerfest LNG

Source: www.gulfoilandgas.com 10/26/2020, Location: Europe

Surveys of the damage after the fire at Hammerfest LNG on 28 September indicates that the LNG plant will be closed for up to 12 months for repairs.

In addition to damage caused by the fire on the air intake on one of the plant's five power turbines, large amounts of seawater from the extinguishing have damaged other auxiliary systems such as electrical equipment and cables in the plant.

It is the scope of work of this consequential damage that are considered the most extensive and the duration of the shutdown will depend on the delivery time of necessary equipment. Progress will also be affected by the current restrictions related to the Covid 19 virus.

"Safety is the first priority and we will not start the plant until we are sure that it can be done in a safe way. Therefore, we have worked systematically and thoroughly to survey the damage after the fire, and assess the technical condition of the plant," says plant director Andreas Sandvik.

"Although a lot of inspection work still remains and there is still significant uncertainty, our best estimate now is that that it may take up until 1 October 2021 to get Hammerfest LNG back into production."

"We will use the shutdown period to also carry out other maintenance and repair work planned for 2021. This includes both ongoing maintenance and maintenance planned in a planned turnaround next spring," Sandvik says.

Equinor, as well as the PSA and the police have started independent investigations of the fire.

"The fire at Hammerfest LNG was a serious incident. The various investigations into the incident will be important in order to identify measures that will prevent similar incidents from happening again," says Grete B. Haaland, senior vice president for Equinor's onshore facilities.

Maintenance and Repair News in Norway >>

Belgium >>  1/20/2021 - DEME's dual fuel trailing suction hopper dredger (TSHD) ‘Scheldt River’ is currently carrying out maintenance dredging work on the Scheldt and during ...
Taiwan >>  1/20/2021 - CWind Taiwan have signed an exclusive cooperation agreement with E&Y Electronics to develop cable maintenance services in the Taiwanese market. This w...

Nigeria >>  1/15/2021 - The Nigerian National Petroleum Corporation (NNPC) has announced that it has received 96 bids from reputable companies that have indicated interest in...
Libya >>  1/12/2021 - At the headquarters of the National Oil Corporation (NOC) in Tripoli, the Chairman of the Board of Directors, Eng. Mustafa Sanalla, received his Excel...

Russia >>  1/11/2021 - Transneft Western Siberia has completed the revamping of the vertical steel floating roof tank (VAFRT) with a volume of 20 thousand m3 at the Parabel ...
Norway >>  1/7/2021 - The Petroleum Safety Authority Norway (PSA) has carried out an audit of Equinor’s management of design engineering and follow-up of barriers for the J...




Norway Oil & Gas 1 >>  2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 |

More News

Related Links

Gulf Oil and Gas
Copyright © 2020 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.