Melbana Provides Operations Update in Block 9, Cuba

Source: www.gulfoilandgas.com 10/28/2020, Location: South America

Melbana Energy Limited is pleased to provide this update on progress made towards the drilling of its two high impact exploration wells onshore Cuba in its Block 9 contract area (“Block 9 PSC”). Melbana has a 30% interest in the 236 million barrels of Prospective Resource (Best Estimate)1 being tested in this drilling program projected to start in March 2021.

Site Preparations
Preparation of the well site for Alameda-1 has completed its third week. Following completion of an aerial photographic survey of the undisturbed sites for the two well pads that are to be built, a survey was undertaken at the first well site to mark the location of the well pad and access roads. Camp facilities were then constructed and crews and machinery arrived on site and commenced work in early October. Construction of the roads and the well pad for Alameda-1 have been slower than projected due to heavy rains but are expected to be completed by the end of the year. Construction of the roads and well pad for the second well, Zapato-1, is planned to commence immediately thereafter. Melbana gives a high priority to safety during field operations. To date there has been no lost time due to injuries or other safety issues.

Funding
Melbana has now received its Past Costs for Block 91, approximately A$5.7 million, in accordance with the terms of the Farm-in Agreement2. These funds have been allocated to Melbana’s net 15% share of the cost of drilling operations in Block 9.

In addition to the above, Melbana has also received into the JV account monies called from its partner to meet anticipated spending requirements for the rest of 2020.

Project Timeline
A tender for the supply of tubulars, casings etc. was completed late last month. Recommendations made by Melbana, as Operator, based on the findings from this process were then approved by the committee representing the joint venture parties and then subsequently submitted to the administration committee for Block 9. Upon receipt of this committee’s approval, contracts will be entered into for the supply of these materials.

The manufacture and supply of some of these items lie on the critical path to the commencement of drilling operations. Subject to an order being placed this month and the accuracy of quoted delivery lead times, drilling operations are forecast to commence in March 2021.

The next order of business following the order of long lead items will be the execution of contracts with drilling and other service providers. Although these do not lie on the critical path, it is our preference to have these agreements completed this year. A final draft of the drilling contract has been completed and is now being circulated amongst relevant stakeholders for their approval prior to signing. Draft agreements have been provided to potential service providers and their commercial proposals are currently being analysed.

Last week, Cuba began relaxing coronavirus restrictions, allowing shops and government offices to open and welcoming locals and tourists at airports across the island (except for Havana). Several Asian and European countries have now resumed flights to Cuba. The wearing of face masks and social distancing remain mandatory, although authorities no longer isolate those who have been in contact with suspected cases of COVID-19.

Given the assumptions and developments summarised above, plans are being made for senior members of Melbana’s Project Management Team to start arriving in Cuba before the end of the year. The rest of the team is projected to arrive, as required, during Q1 2021.

Melbana is in the process of developing a contingency plan that should allow drilling operations to continue should coronavirus restrictions be reinstated over the course of next year.

Melbana Energy’s Executive Chairman, Andrew Purcell, said:
“Activity towards the commencement of drilling operations is now fully underway and we look forward to providing regular updates as milestones are reached. We have an experienced project team eager to deliver this project on time and within budget and look forward to finally testing these exciting prospects.”


Australia >>  12/5/2024 - - Drilling commenced on 5 December at the West Mereenie 29 (WM29) development well
- WM29 is the first of a two well deve...

Iraq >>  12/4/2024 - The technical and engineering staff of the Iraqi Drilling Company completed the drilling and reclamation of 12 oil wells during the past month of Nove...

Colombia >>  12/2/2024 - Canacol Energy Ltd. (“Canacol” or the “Corporation”) is pleased to provide the following update concerning its ongoing exploration and development dri...
Equatorial Guinea >>  11/29/2024 - Panoro Energy ASA (“Panoro” or the “Company”) can confirm that drilling of the S-6 (“Akeng Deep”) exploration well at Block S offshore Equatorial Guin...

United States >>  11/29/2024 - TomCo the US operating oil development group focused on using innovative technology to unlock unconventional hydrocarbon resources, announces that its...
Canada >>  11/27/2024 - Helium Evolution Incorporated ("HEVI" or the "Company"), a Canadian-based helium exploration company focused on developing assets in southern Saskatch...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.