Marubeni Corporation and Osaka Gas Co., Ltd established a special purpose company, Aichi Tahara Biomass Power Plant G.K. to develop a wood-based power plant, Aichi Tahara Biomass Power Plant, in Tara City, Aichi Prefecture.
This project will cover the construction and operation of a wood-based dedicated biomass power plant with a power generation output of 75MW in Tahara City, Aichi Prefecture, and the sale of the generated electricity. We will aim for the start of power plant operations in October 2024 with the understanding and cooperation of the local population and other related parties.
?About Aichi Tahara Biomass Power Plant?
Place Part of Tahara 4 in the coastal industrial zone of Tahara City, Aichi Prefecture
Power Generation Output 75MW
Fuel Type Wood pellet
Construction start Date September, 2021
Commercial Operation Date October, 2024
?About Tahara Biomass Power Plant G.K.?
Representative Officer Performing Duties
Seishi Narita(Marubeni Clean Power Corporation)
Head Office 2-7-1, Nihonbashi, Chuoku, Tokyo
Established November 28, 2016
Business Construction and operation of wood-based biomass power plant, supply and sale of electricity etc.
Investment Marubeni Clean Power Corporation?(37.5%)?JKE(37.5%)Osaka Gas(25%)
?Marubeni has invested in through its wholly owned subsidiary Marubeni Clean Power Corporation