Aker BP – Organization & Follow-up of Responsibility for Helidecks

Source: www.gulfoilandgas.com 3/26/2021, Location: Europe

The Petroleum Safety Authority Norway has carried out an audit of Aker BP and their organization and follow-up of responsibility for helidecks.

The audit was conducted from 12 to 16 October 2020 with assistance from the Civil Aviation Authority Norway.

Objective
The objective of the audit was to ensure that Aker BP is undertaking systematic work to reduce the risk associated with helicopter operations on the company’s offshore facilities.

Result
The reports from the Civil Aviation Authority Norway cover non-compliance with the regulations relating to helicopter operations – use of offshore helidecks (BSL D 5-1). These are published in a separate report prepared by the Civil Aviation Authority Norway.

The Petroleum Safety Authority Norway did not identify any non-conformities during the audit.

Four improvement points were identified, relating to:
• Competence requirements
• Training of response teams onboard the flank facilities
• Follow-up of internal requirements for emergency preparedness training
• Marking of evacuation routes

What happens next?
We have asked for the company's assessment of the observations we have categorized as improvement points.

For its part, the Civil Aviation Authority Norway will follow up the non-conformities with the helicopter companies.


Norway >>  4/26/2021 - Siem Offshore has been awarded a 40 days firm contract plus options, in addition to mobilization and demobilization fees, for the MPSV "Siem Dorado" f...
United States >>  4/23/2021 - The Company is very pleased to see the reaffirmed trust placed by a key client within the subsea construction segment, which underlines the Company’s ...

Belgium >>  4/22/2021 - Euronav NV has entered into an agreement with the Hyundai Samho yard for two VLCC newbuilding contracts. Sourcing fleet renewal from the newbuilding m...
Greece >>  4/22/2021 - Diana Shipping Inc., a global shipping company specializing in the ownership of dry bulk vessels, announced that, through a separate wholly-owned subs...

Norway >>  4/22/2021 - The first part of the construction of the Hywind Tampen concrete foundations was finalized this week at Aker Solutions’ yard in Stord, Norway. The 11 ...
Trinidad and Tobago >>  4/22/2021 - Reach Subsea ASA (“Reach”) has been awarded a call-off under our frame agreement with BP for 2021 execution, representing about 80 project days.





Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.