Offshore Part of One Line of Nord Stream 2 Has Been Mechanically Completed

Source: www.gulfoilandgas.com 6/10/2021, Location: Asia

The offshore part of one line of Nord Stream 2 has been mechanically completed. Pipelay was completed on June 4, 2021, and the above water tie-in was performed – the offshore pipeline sections laid from Russia and Germany have thus been interconnected.

Starting from tomorrow, the required pre-commissioning activities will be carried out to prepare for gas-in.

Offshore pipelay works on the second line are ongoing. All activities are in accordance with the respective permits.


East Timor >>  7/7/2021 - McDermott International, Ltd announced it has been awarded a Subsea, Engineering, Procurement, Construction and Installation (EPCI) contract from Sant...
India >>  7/5/2021 - Aker Solutions has signed a contract with Crown LNG for front-end engineering and design (FEED) for the Kakinada LNG regassification project offshore ...

China >>  6/30/2021 - Qatar Petroleum entered into a long-term Sale and Purchase Agreement (SPA) with Shell for the supply of 1 million tons per annum (MTPA) of LNG to the ...