Var Energi – Jotun FPSO – Project Management & Project Follow-up after PDO

Source: www.gulfoilandgas.com 7/8/2021, Location: Europe

The Petroleum Safety Authority Norway (PSA) has carried out an audit of Var Energi and their organisation and implementation of project management for the upgrading and life extension of Jotun A (Jotun FPSO). The audit was conducted on 3 and 4 June 2021.

Background
The work that the companies undertake to plan and execute projects is important for the quality, safety and the working environment of the finished product.

Deficiencies in project management can lead to unintended negative HSE outcomes whether due to overly optimistic plans, underestimates or discrepancies between the actual status and what appears in the documentation. This may have consequences for compliance with safety and working environment requirements because such project-related risks can have a negative impact on:
• emphasis on quality considerations in the project moving forward
• quality of technical deliveries
• arrangements for safe start-up and operation

The audit covered Var Energi's planning, follow-up and management of remaining works until the Jotun FPSO is taken out to its new location. This included:
• Information gathering and sharing for planning of the activities, decision support and analysis
• Plan for the implementation of remaining works
• Coordination between different levels and areas, assessment of the degree of maturity of design documentation and scope of work, and coordination between engineering and production
• Assessment of HSE risks and measures for safe start-up and operation

Objective
The objective of the audit was to verify that the project is being carried out in accordance with the company's requirements and the HSE regulations, and that, through its project management, Var Energi is ensuring that, in the project execution phase, they are reducing risk and preventing accidents during the start-up and operational phases.

Result
One non-conformity related to planning and one improvement point related to follow-up were identified.

What happens now?
We have asked Var Energi to report by 1 September 2021 on how the non-conformity will be addressed and for an assessment of the improvement point observed.


Guyana >>  9/13/2021 - The ABS-classed Liza Unity FPSO has been awarded the SUSTAIN-1 notation by leading Classification Society ABS – the first FPSO in the world to receive...
Australia >>  9/10/2021 - BW Offshore is pleased to announce a partnership with international global infrastructure investors for the equity financing of the FPSO for the Baros...

Guyana >>  9/9/2021 - Keppel Offshore & Marine’s (Keppel O&M) wholly-owned subsidiary Keppel Shipyard Ltd (Keppel Shipyard) has delivered the Liza Unity, a mega Floating Pr...
Canada >>  9/8/2021 - Suncor announced that the co-owners of the Terra Nova Floating, Production, Storage and Offloading (FPSO) facility and associated Terra Nova Field (“T...

Brazil >>  9/3/2021 - SBM Offshore is pleased to announce that it has signed with Petróleo Brasileiro S.A. (Petrobras) the Letter of Intent for a 22.5 years lease and opera...
China >>  9/1/2021 - Shanghai Waigaoqiao Shipbuilding Co., Ltd., a subsidiary of China State Shipbuilding Corporation, built the fourth H1499 ship of the Fast4Ward® "unive...




Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.