IOG Provides Corporate and Operational Update

Source: www.gulfoilandgas.com 11/22/2021, Location: Europe

IOG, the Net Zero UK gas and infrastructure operator focused on high return projects, has provided a corporate and operational update, with a short accompanying presentation available here: https://bit.ly/3Hwbbuk

Andrew Hockey, CEO of IOG, commented:

'The offshore subsea and hook-up scopes for the Blythe and Elgood fields are now complete. We continue to work closely with Bacton terminal operator Perenco and an enlarged workforce to complete the reception facilities recommissioning and deliver First Gas in Q4, albeit this may be challenging.

Meanwhile, we expect the Noble Hans Deul rig to re-mobilise to Southwark in early December once it has been re-certified for safe operation, with Southwark First Gas still on track for Q2 2022.

Phase 1 looks set to capitalise on very strong gas prices whilst also providing timely new low carbon intensity UK domestic gas production. I would like to thank the whole IOG team and all our contractors for their continued dedication and hard work towards delivering a safe and reliable start-up which will be a major milestone for the company.'

Schedule

The Saturn Banks Project Phase 1 passed one million cumulative manhours worked in September 2021. Despite recent Covid-19 related challenges both offshore and onshore, the Company continues to target safe and reliable delivery of First Gas by the end of Q4 2021, subject to completion of the remaining onshore scope detailed below.

The Noble Hans Deul rig owner has progressed investigation and repair works of the rig leg at Dundee port to allow safe resumption of Phase 1 drilling. Repair operations have required equipment and personnel to be mobilised from the Middle East and Asia. The rig is expected to re-mobilise to Southwark by the first week of December, subject to weather, and Southwark First Gas remains on track for Q2 2022. All permits are in place to start Southwark drilling and the IOG drilling and subsurface teams have used the downtime to accelerate planning of the 2022 appraisal well campaign.

Phase 1 Offshore

The key subsea, umbilicals, risers and flowlines (SURF) and hook up and commissioning (HUC) scopes have now been completed in preparation for Blythe and Elgood first gas. These include connection of the Blythe 12" pipeline (PL4956) and Elgood 6" pipeline (PL4955) to the Blythe platform risers and leak testing and dewatering of both pipelines; fabrication and installation of the 24" valve skid at the Saturn Banks tie-in point; tie-in of the shoreward section (PL5079) of the 24" Saturn Banks pipeline section at Bacton; hook-up of the Blythe and Elgood wells and system commissioning. Use of a walk to work vessel has enabled longer shift durations and minimised the need for helicopter flights.

Successful leak testing and dewatering of the 24" pipeline and valve skid has now confirmed the integrity of the production system from the onshore Saturn Banks Reception Facilities (SBRF) at Bacton to the Blythe platform and the Elgood subsea well. Once the onshore scope is finished, along with final systems testing between on and offshore, nitrogen venting and backgassing of the pipelines will enable start-up of the Blythe and Elgood wells in quick succession. Analysis of the early months of production will then help to facilitate production guidance for 2022.

Phase 1 Onshore

At the SBRF, an expanded team has been progressing refurbishment activities. Key items recently completed include installation of the new 24" emergency shutdown valve, pipeline spools and motorised valves, replacement of the gas metering streams and associated isolation valves, installation of new pressure control valves and pulling/terminating of all multi-core cables. IOG is co-operating closely with Perenco UK Limited and the onshore contractors to expedite completion of intra-terminal pipework, testing of telecoms & control systems, installation of the emergency vent stack, in order to enable a safe and reliable start-up at the earliest feasible time.

Appraisal Planning

Planning and contracting is underway for the two 2022 appraisal wells at Kelham North / Kelham Central (P2442: Block 53/1b) and Goddard (P2342: Block 48/11c and 12b) respectively. The Company has exercised its contract option to drill these wells in succession with the Noble Hans Deul rig after the second Southwark well, on the same competitive dayrate as the Phase 1 wells. Petrofac has been appointed Well Operator for the two appraisal wells and pre-drill site surveys are being planned for Q1 2022. In parallel, analysis of reservoir and production data from the Southwark 1 and 2 wells will inform an optimal Southwark 3 well plan.

Further Phase Activities

Concept select work on Nailsworth is progressing with a view to accelerating front-end engineering and design (FEED) and taking a Final Investment Decision (FID) in Q1 2022. P2589 (Panther / Grafton area) seismic reprocessing is also starting shortly and expected to be completed by mid-2022, providing an enhanced subsurface view of the area directly east of Southwark and Elland.

Gas Market and Risk Management

The UK NBP benchmark, like other global gas markets, has been exceptionally strong in 2021. Forward pricing remains substantially above the Company's planning case, although volatility also remains high. Preparatory discussions are underway with relevant parties to start implementing a prudent, systematic gas hedging strategy by the end of Q1 2022.


Germany >>  8/18/2022 - Neptune Energy announced drilling has begun on a new production well at its operated Romerberg oil field in the Rhine Valley, south-western Germany....
United States >>  8/18/2022 - An oil exploration and production firm called Laredo Oil, Inc. (LRDC) ("Laredo Oil") announced that its wholly owned subsidiary, Lustre Oil Company, L...

Norway >>  8/15/2022 - The Norwegian Petroleum Directorate (NPD) has granted PGNiG Norway Upstream AS drilling permit for well 6608/1-1 S, cf. Section 13 of the Resource Man...
Norway >>  8/12/2022 - Aker BP ASA, operator of production licence 941, has concluded the drilling of wildcat well 6507/3-15.

The well was drilled about 14 km nor...


Australia >>  8/9/2022 - Central Petroleum Limited (“Central”) advises that as at 0600 hrs ACST on 8 August 2022, the Palm Valley 12 (PV12) well in OL3, Southwest of Alice Spr...
Norway >>  8/9/2022 - The Petroleum Safety Authority Norway has given Equinor consent for exploration drilling in block 6507/8 in the Norwegian Sea.

Operator: E...





Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.