Production Testing Re-starting at Reid’s Dome

Source: www.gulfoilandgas.com 11/30/2021, Location: Not categorized

State Gas Limited (GAS) advises that production enhancement works have been completed at the Nyanda-8 well and a production test of the re-completed well commenced on 28 November 2021. Production enhancement works are well advanced at the Serocold-1 well and weather permitting, a production test of this well is expected to commence early next week.

State Gas is currently undertaking works at its Reid’s Dome and Rolleston-West Gas Projects in Central Queensland to progress the projects towards delivering new gas supplies to meet forecast shortfalls in the east coast Australian gas market. Activities at Reid’s Dome are aimed at enhancing production from the Serocold-1 and Nyanda-8 wells to the levels achieved by the very successful Nyanda-4 well, while at Rolleston-West the Company is carrying out the first production test in the area, at the Rougement-2 well.

At Nyanda-8 the coal seams have been jetted to expand the area of formation accessible by the well bore. The Company is carefully monitoring the well as the water level is lowered and downhole pressures reduced to allow the gas to desorb.

At Serocold-1 the Company has completed a foam squeeze to seal off the non-producing zones in the well and facilitate better pump operation. The pump will now be installed, and the production test of the newly configured well commenced.

At Rougemont-2 the production test is ongoing, with the performance of this first test in the area being monitored closely and pumping carefully controlled to optimise production outcomes.

“I am very much looking forward to the results of these new production tests” said Company Executive Chairman Richard Cottee.

“Every new domain – as Reid’s Dome is – requires its ‘code’ to be ‘cracked’, with the best production method the result of ‘tweaking the levers’”, he said.

“We know Reid’s Dome contains a lot of gas, we just need to optimise its release from the plethora of coal seams. If these new tests produce the way I am expecting we will be on our way to getting our gas to market.”

State Gas will continue to provide updates as activities progress.


Australia >>  5/23/2022 - • Flow testing package has been mobilised and is being rigged up at the SE-1 well site with perforation and subsequent flow testing expected to start ...
Australia >>  5/18/2022 - • Hydraulic stimulation of Carpentaria-2H is expected to commence in late June 2022
• Hydraulic stimulation is expected to take 15 to 20 days fo...


Australia >>  5/11/2022 - The Operator of the Cue’s Amadeus Basin assets, Central Petroleum has recently provided updated information to the joint venture on the Palm Valley an...
Philippines >>  5/5/2022 - • Production alliance agreed with Asian Based Specialists
• Covers Extended Well Tests and Early Production Systems

Sacgasco Limited...


China >>  5/4/2022 - Empyrean Energy plc ("Empyrean"), the oil and gas development company with interests in China, Indonesia and the United States, provides the following...
Egypt >>  5/4/2022 - SDX Energy Plc (SDX), the MENA-focused energy company, is pleased to announce the completion of the tie-in of the SD-5X Warda well (SDX Working Intere...




Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.