Kinetiko Energy Provides Operations Update

Source: www.gulfoilandgas.com 12/7/2021, Location: Africa

Highlights
• Three wells of Korhaan Project successfully spudded.
• Each well has been drilled into the dolerite sills and Korhaan-4 has been cased to 150m and cementation operations are underway.
• Each well has shown a gas presence towards the bottom of the dolerite cap rock structure, where mudstone and sandstone samples have been found.
• Significant rain and electrical storms over the last 14 days and procurement of cementing tools have caused drilling delays.
• Korhaan-4 well is expected to commence drilling into the gassy sandstone and underlying coal seams to TD within the next few days.
• Korhaan-5 will start running casing imminently in preparation to commence drilling the production section.
• Further drilling on Korhaan-3 is expected to be resumed in January 2022 after the Christmas shut-down.
• The Aeromagnetic survey covering 564km2 over selected portions of ER 270 and ER 272 have successfully completed.

Perth-based energy exploration company Kinetiko Energy Limited is pleased to update that it’s exploration drilling on the Korhaan Project and completion of aeromagnetic surveys flown The three new wells of the Korhaan Project have been successfully spudded and each well has been drilled into the dolerite sills and Korhaan-4 has been cased to 150m and cementation operations are underway. Korhaan-4 well is expected to commence drilling into the gassy sandstone and underlying coal seams to TD within the next few days while well Korhaan-5 will start running casing imminently and continue drilling the production section.

The Korhaan-3 well is drilled to 102m and has been temporarily suspended in preference to an attempt to complete Korhaan-4 and Korhaan-5 before the end of the year. Drilling on Korhaan-3 is expected to be resumed in January 2022 after the Christmas shut-down period.

Very heavy thunderstorms with consequent lightning, hail and rain has resulted in substantial delays to the Company’s operations. This seasonal weather has been worse than normal. Following HSE Policy, requirements are to down-mast the drilling rigs once lightning approaches 20km from site. This has proven to be prudent given the high storm count which has swept drilling sites.

Preliminary gas flow rates will be assessed following the wireline logging and the barefoot completion of each well, and could be reassessed following the possible cased completion plan in 2022.

The company has completed the aeromagnetic survey which flew approximately 13,479 line kilometres covering 564km2, over selected portions of ER 270 and ER 272 which form the most Southern and Northern extensions of the Company’s exploration rights.

Results from the completed survey have been received and are anticipated to be processed during December and January 2022 and expectations are to build significantly on the existing 37 identified prospective gassy compartments and assist target further areas for well tests and pilot production fields.

This announcement is authorized for release to the market by the Board of Directors of Kinetiko Energy Limited.


Canada >>  5/19/2022 - PetroTal Corp. is pleased to announce that Q1 2022 results will be released on May 26, 2022, along with an extended investor webcast. Additionally, th...
Egypt >>  5/18/2022 - SDX Energy Plc (SDX) is pleased to announce the spudding of the MSD-24 infill development well on the Meseda field. This well is the fourth in a fully...

Australia >>  5/16/2022 - Highlights
- Drilling of Glenaras 28 complete
- Well encountered 27m of gassy coals
- Steps underway to mitigate impact of further uns...

United Kingdom >>  5/13/2022 - UK Oil & Gas PLC has announced that the North Sea Transition Authority (formerly the Oil and Gas Authority) has granted a one-year extension to the ag...

Australia >>  5/12/2022 - Western Gas has provided an operational update on the drilling of the Sasanof-1 exploration well and will issue further updates upon the completion of...
Norway >>  5/12/2022 - Aker BP ASA, operator of production licence 685, has concluded the drilling of wildcat well 35/4-3.

The well was drilled about 20 kilometre...





Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.