Wärtsilä Power Plant Upgrade & Extension will Enable Production Expansion for Largest Gold Mine

Source: www.gulfoilandgas.com 8/16/2022, Location: Africa

The technology group Wärtsilä will supply an 18 MW extension to the power generating facility and upgrade the electrical and automation system of the existing power plant at the Sabodala-Massawa gold mine complex in Senegal, West Africa. The mine is owned by Endeavour Mining, a leading global gold producer. The upgrading and extension project will allow for the complete integration of all the site’s power generating capacity, while ensuring the availability of the needed electric power to maintain and expand the mine’s production schedules.

The order with Wärtsilä was placed by Sabodala Gold Operations and it has been booked in Wärtsilä’s order intake in Q3 2022. The project will be delivered under a complete engineering, procurement and construction (EPC) contract.

The Sabodala-Massawa mine is the largest producing gold mine in Senegal and is located in the eastern part of the country in the Kedougou region. Endeavour's planned mine expansion will transform Sabodala-Massawa into a top-tier gold asset with incremental production.

“Wärtsilä has a depth of experience in delivering power solutions for mining operations around the world. Not being connected to the grid means that the captive plant has to be capable of providing a reliable supply of electricity at all times, since no power equals no production. The Wärtsilä 32 engines selected for this expansion project have established a strong reputation for high efficiency and reliability under even the most difficult ambient conditions, eliminating revenue losses from power shortages,” said Marc Thiriet, Energy Business Director, Africa West, Wärtsilä.

The three Wärtsilä 32 engines to be installed are 20 per cent more fuel efficient than the plant’s existing engines. Their fuel efficiency minimises the environmental impact by reducing harmful CO2 emissions. In addition to their outstanding performance, they have the flexibility to support a smooth transition to the integration of solar power and energy storage into the system. The upgrade of the electrical and automation system will optimise the interconnection and control for the existing power plant with the extension.

The project is expected to be completed and commissioned before the end of 2023.

Wärtsilä is Senegal’s leading provider of power generating equipment, and already has 543 MW of installed capacity in altogether 20 power plants in the country. 458 MW of this capacity is under Wärtsilä long-term service agreements.


Ireland >>  9/27/2022 - Hydrokinetic solutions provider GKinetic Energy Ltd has concluded a pivotal deployment of its 12kW unit at Strangford Lough, Northern Ireland. The dep...
Spain >>  9/22/2022 - Mango, one of Europe's leading groups in the fashion industry, and ACCIONA Energía, the world's largest 100% renewable energy company with no fossil l...

United States >>  9/22/2022 - Six Rhode Island cities and towns have joined together to launch aggregation programs that leverage community-wide buying power to provide their resid...
United States >>  9/22/2022 - Nearly 130,000 homeowners and renters across northern Illinois saved a total of approximately $17.5 million on their energy bills, based on 2021 rates...

United States >>  9/22/2022 - WattBridge Energy, LLC announced financial closing for 480 MW of firm dispatchable generation for ERCOT. The transaction includes the company's sixth ...
Australia >>  9/20/2022 - FEX Global, which operates a licensed Australian Futures Exchange this week successfully launched its $500 Strike 5MS Cap Power Quarterly Futures and ...




Gulf Oil and Gas
Copyright © 2021 Universal Solutions All rights reserved. - Terms of Service - Privacy Policy.