Weekly Drilling Report January 5, 2022

Source: www.gulfoilandgas.com 1/6/2023, Location: Europe

WELL: Guluc-2
Spudded December 10, 2022. Days since spud: 26
Progress: 1404 metres
Measured Depth: 3199 metres

Week Summary:
Drill 12 ¼” x 13” hole to 3199 metres – ROP 18 to 26 metres/hour

Further Activities:
Drill 12 ¼” x 13” hole to MD of 3300 metres
Put in and cement 9 5/8” intermediate casing
Wait on cement to dry, drill out plugs
Drill 8 1/2” x 9” hole from MD 3300 metres to about MD of 4000 metres (TD)
Put in and cement 7” casing
Wait on cement
Evaluate Logging While Drilling (LWD) data to pick perforation intervals
Perforate and test gas zones.
Turn over to Production Operating Partner


Canada >>  11/6/2024 - Helium Evolution Incorporated (TSXV:HEVI) ("HEVI" or the "Company"), a Canadian-based helium exploration company focused on developing assets in south...
Norway >>  11/4/2024 - The Norwegian Offshore Directorate has granted Vår Energi ASA drilling permit for wellbore 7122/9-2 in production licence 1131, cf. Section 13 of the ...

China >>  10/31/2024 - China Petroleum Network News (Special Correspondent Zhang Qiuliang and Zhang Wenqiong) On October 28, at the construction site of the GY16-Q9-H25 well...
Mongolia >>  10/31/2024 - The second pilot production well (LF-06) has been successfully drilled and cased to a total depth of 475 metres
? LF-06 intersected approximatel...


United States >>  10/30/2024 - Helix Exploration, the helium exploration and development company focused on helium deposits within the 'Montana Helium Fairway', is pleased to announ...
Canada >>  10/28/2024 - Tuktu Resources Ltd. (TSXV: TUK) ("Tuktu" or the "Company") is pleased to provide an operational update on its discovery well. ...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.