Weekly Drilling Report February 12, 2022
Source: www.gulfoilandgas.com 2/3/2023, Location: Europe
WELL: Guluc-2
Spudded December 10, 2022. Days since spud: 53
Progress: 0
Measured Depth: 3910 metres
Week Summary:
Run in the 7” casing
Cement the casing and wait on cement
Evaluate Logging While Drilling data to pick perforation intervals
RIH with casing scraper to prepare borehole for completion string
Further Activities:
RIH with perforation guns
Perforate intervals (most likely lower most zones) and test well
Turn over to Production Operating Partner
Side RIG over a few feet to continue with the West Akcakoca-1 well, which already has 1008 metres of surface hole drilled.
The well Guluc 2, as per the news release, has 73 metres of gas sand reservoir. Guluc 2 was placed about 200 metres north of the old Guluc 1 well to target a better seismic AVO anomaly. Guluc 2 was a pleasant surprise as Guluc 2 well had 73 metres of gas sand reservoir compared to Guluc 1’s about 20 metres. Guluc 2 appears to be an excellent gas well.