WELL: West Akcakoca-1
Days since move: 29
Progress: 115 metres
Measured Depth: 3839 metres
Week Summary:
Drill 8 ˝” x 9” hole to 3839 TD
Evaluated the Logging while drilling data to define gas pay
Prepare the borehole to receive the 7” casing and hangers
Run in and cement 7” casing and WOC (wait on cement)
Clean wellbore and prepare for completion string
Petrophysical analysis completed to pick perforation intervals.
Further Activities:
Run in completion string, set packer, perforate, test and turn over to production
Skid back over to Guluc 2 to perforate, test and turn over to production
55 metres of gas pay: upward surprise, which makes two now as Guluc 2 had 73 metres of gas pay, which gives a combined total for the two wells of 128 metres of gas pay.