The Petroleum Safety Authority Norway (PSA) has carried out an audit of ConocoPhillips and their project management and project follow-up pursuant to the plan for development and operation (PDO) for Tommeliten A. The audit was conducted on 20 and 21 April 2023.
Objective
The objective of the audit was to verify that the project is being carried out in compliance with the HSE regulations, and that, through its project management, ConocoPhillips is ensuring that, in the project execution phase, they are reducing risk and preventing accidents during the start-up and operational phases.
Result
No non-conformities or improvement points were identified during this audit.