The AER Fines AlphaBow Energy Ltd. for Unauthorized Pipeline Construction

Source: www.gulfoilandgas.com 7/13/2023, Location: North America

The Alberta Energy Regulator (AER) has ordered AlphaBow Energy Ltd. (AlphaBow) to pay a $25 000 fine for constructing pipelines without approval.

Between November 11 and 17, 2021, AlphaBow performed work to construct two pipeline segments, near Hardisty, Alberta. The AER became aware of AlphaBow’s actions on November 17, 2021, when the company submitted a notification for a pipeline pressure test to the AER, leading to an inspection of the pipelines by the AER.

While AlphaBow had applied for pipeline licences, the AER had not approved the applications prior to construction. As a result, the AER ordered the company to stop work, issued two notices of noncompliance, and launched an investigation. Based on the investigation findings, the AER is taking enforcement action against AlphaBow by issuing a fine.

A fine—or an administrative penalty—is one enforcement tool the AER can use when companies break the rules. The penalty amount is based on an assessment of the seriousness of the contravention and the effect (or potential effect) it has on public safety, the environment, or resource production.

Before constructing energy-related infrastructure, such as pipelines, companies must apply to the AER for the necessary licence. This process enables the AER to assess the risks and effects associated with the activity, which is fundamental to ensuring the safe and responsible development of energy resources within Alberta. In this case, AlphaBow did not obtain licences under the Pipeline Act, prior to construction.


Finland >>  2/15/2024 - Gasgrid Finland and the Estonian gas network operator Elering noticed an unusual drop in pressure in the Balticconnector undersea gas connection pipe ...
Netherlands/Holland >>  2/1/2024 - Following preparations lasting about five years, 2024 year marks the start of the gas pipeline conversion between the Dutch towns of Emmen and Ommen. ...

Canada >>  1/31/2024 - The Commission of the Canada Energy Regulator issued its reasons for approving Trans Mountain’s variance application for the Mountain 3 horizontal dir...
Canada >>  1/31/2024 - The Commission of the Canada Energy Regulator issued its reasons for approving Trans Mountain's variance application for the Mountain 3 horizontal dir...




Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.