Eskom constructs & activates alternative 132kV power line for Central Karoo contingency

Source: www.gulfoilandgas.com 3/2/2024, Location: Africa

Eskom Distribution in the Western Cape is pleased to announce the successful construction and livening up of the alternative 132kV power line which will provide a contingency to our valued customers in the Central Karoo, allowing for seamless rerouting of electricity when necessary. This significant milestone achieved at 23:40 on 29 February 2024, marks a crucial step in ensuring uninterrupted power supply to the towns of Sutherland, Roggeveld, Laingsburg, Ladismith, Leeu Gamka, Swartberg, Merweville, Matjiesfontein, Prince Albert, Fraserburg, and surrounding areas.

“Our primary goal is to maintain a reliable and resilient electrical network that meets the needs of our community,” stated Mbulelo Yedwa, Eskom General Manager, Cape Coastal Cluster. “The activation of the 132kV temporary bypass reaffirms our dedication to ensuring uninterrupted power supply, especially during critical maintenance and adverse weather patterns like recently,” Yedwa added.

The implementation of this contingency plan follows a severe storm on the night of 03 February 2024, which caused widespread damage to critical infrastructure, resulting in a large-scale power outage lasting approximately two weeks. While all affected areas were fully restored by 15 February 2024, Eskom proactively designed a plan to mitigate the impact of such incidents in the future.

The activation process involved rigorous testing, inspection, and adherence to standards to ensure the safety and effectiveness of the contingency measures. Eskom employees have been working tirelessly to complete this part of the project. Despite facing challenges and adverse weather conditions, Eskom employees demonstrated exceptional professionalism and resilience in delivering the project within the stipulated timeframe.

As Eskom Distribution moves forward, the commitment to innovation and excellence in electricity distribution remains steadfast, with a focus on meeting the evolving needs of customers and communities.


United Kingdom >>  1/15/2025 - Grid connections applications have continued to grow over the last year to the point that it is no longer possible to deliver connections reforms in p...
United States >>  1/15/2025 - Anax Power announces the successful commissioning of the 500kW Anax Turboexpander (“ATE-500”), which uses the pressure and flow of natural gas moving ...

United States >>  1/14/2025 - Qmerit, North America's leading provider of implementation solutions for EV charging and other electrification technologies, is announcing the launch ...
United States >>  1/14/2025 - The U.S. Department of Energy’s (DOE) Office of Electricity (OE) today announced a Request for Information (RFI) to guide future planning of OE’s Appl...

United Kingdom >>  1/13/2025 - Mast Energy Developments PLC is pleased to announce an update regarding its Pyebridge flexible power generation asset, the highlights and details of w...
United Kingdom >>  1/13/2025 - Notice under section 6A(5) of the Electricity Act 1989 of the grant of an electricity generation licence

The Gas and Electricity Markets Au...





Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.