7/28/2023 - WELL: Alapli-2 Progress: 0 metres Measured Depth: 3258 metres Week Summary: 1. Cleaned and scraped well 2. Set packer and tested Further Activities: ... |
7/21/2023 - WELL: Alapli-2 Progress: 0 metres Measured Depth: 2885 metres Week Summary: Finished cementing casing and waiting on cement to dry Further Activities: ... |
7/14/2023 - WELL: Alapli-2 Progress: 0 metres Measured Depth: 2885 metres Week Summary: 1. Run in and cement intermediate casing 2. Drill out plugs Further Activities... |
7/7/2023 - WELL: Alapli-2 Progress: 511 metres Measured Depth: 2885 metres Week Summary: Drill 12 Ό x 13 hole to 2885 metres MD Prepare hole to run in intermediate casin... |
6/23/2023 - WELL: Alapli-2 Progress: 903 metres Measured Depth: 903 metres Week Summary: Run in and cement surface casing. Further Activities: Drill next section ... |
6/16/2023 - WELL: Alapli-2 Progress: 903 metres Measured Depth: 903 metres Week Summary: 1. Mob to Akkaya tripod and spud Alapli-2 well 2. Run in the conductor pipe 3... |
6/9/2023 - Trillion Energy International Inc. announces the spudding of the Alapli-2 natural gas well at the SASB gas field, offshore Turkey, the sixth well in the Companys multi-well program. Alapl... |
6/2/2023 - WELL: Alapli-2 Rig is currently down rigging Progress: 0 meters Measured Depth: 0 metres Week Summary: 1. Perforated and tested Bayhanli-2, turned over to Produc... |
5/26/2023 - WELL: Bayhanli-2 Progress: 0 meters Measured Depth: 3425 metres Week Summary: Clean and scrap 7 casing Run in with production tubing. Set Packers |
5/19/2023 - WELL: Bayhanli-2 Progress: 259 meters Measured Depth: 3425 metres Week Summary: Drill out and drill new 8 ½ hole to 3425 metres Run in 7 casing and cement |
5/17/2023 - Trillion Energy International Inc. is pleased to announce the preliminary gas indications from the Bayhanli 2 well, the fifth well in our multi-well program at the SASB gas field, Black Sea, Turkiye. ... |
5/12/2023 - WELL: Bayhanli-2 Progress: 464 meters Measured Depth: 3268 metres Week Summary: 1. Continue to drill 8 ½ hole to 3400 metres 2. Conditions hole, run in 7 casing ... |
5/5/2023 - WELL: Bayhanli-2 Measured Depth: 2804 metres Week Summary: 1. Condition 12 1/24 x 13 hole for 9 5/8 casing to 2804 metres measured depth. 2. RIH 9 5/8 casing to 2300 ... |
4/28/2023 - WELL: Bayhanli-2 Progress: 1746 meters Measured Depth: 2804 metres Week Summary: Drilled 12 1/2 x 13 hole for 9 5/8 casing to 2804 metres measured depth, which is... |
4/18/2023 - UK Oil & Gas PLC (UKOG) is pleased to announce that Pinarova-1's 9 inch casing is now set and cemented down to 287 metres below surface. In preparation for drilling ahead through the target Eocene Hoy... |
4/14/2023 - WELL: Bayhanli-2 Progress: 496 meters Measured Depth: 496 metres Week Summary: Spud Bayhanli 2 well Drill, case and cement 13 3/8 casing Further Acti... |
4/11/2023 - UK Oil & Gas PLC (London AIM: UKOG) is pleased to announce that Pinarova-1 drilling operations commenced at 0800 local time on Friday 7th April, 2023. Drilling of 12Ό inch diameter hole down to the fi... |
4/7/2023 - WELL: Bayhanli-2 Progress: 0 meters Measured Depth: Week Summary: 1. RIG down and start mobilization to East Ayazli Tripod 2. Performed positioning to East Ayazli ... |
3/31/2023 - UK Oil & Gas PLC is pleased to announce that construction of Pinarova-1's drilling pad and access road has now been completed. Drilling to a total depth of around 500-550 metres below surface is now e... |
3/24/2023 - WELL: West Akcakoca-1 Days since move: 36 Progress: 0 metres Measured Depth: 3839 metres Week Summary: 1. 7 casing liner cemented 2. Clean wellbore for packer... |