Scope
The company announces its need for Main Distribution Power Center.

1- Main Distribution Power Center supplied with following specifications:-
a- The M.D.P.C should be supplied by two incoming feeders and bus tie with auto-manual transfer
b- Emergency generator circuit breaker should be supplied with mechanical & electrical interlock with both two incoming feeders
c- Air circuit breakers with draw able type should be used for all Incomings, bus section and outgoing feeders d- The incoming, bus section & outgoing breakers are with manual and electrical closing mech. And should be contain their analogue ammeters, voltmeters selector switches, over current, earth fault and short circuit tripping device.
e- Power factor correction on both sides to keep the P.F with the range 0.9-0.95 lag (the exist 300KVAR for each side)
f- The MDPC should be with the following specifications:-
1- The switchgear rating at 50C° ambient.
2- Rated voltage l000v & Operating voltage 400v.
3- Short circuit level for 1 sec 80 KA.
5- Control voltage 220VAC, 50 Hz, phase +neutral.
6- Main incomers should be containing multifunction meter.
7- Ingress protection IP43
8- MDPC supply

2-Motor Control Center (MCC) Supplied with following specifications:-
a- MCC provided with all required metering and indications.
b-MCC contains the motors starters with draw able type for both Power and control cables, all starters D.O.L and provided with:-
1- High breaking capacity MCCB for short circuit protection.
2-Magnetic air breaks contactor.
3- Over load relay.
4- Analog ammeter as well as C.T for remote Ammeter.
5-Start, stop, and reset .B.P'S & Indication lamps for ON-OFF-TRIP.
6- Control voltage shall be 220V, 50HZ,
C- The MCC should be with the following specifications:-
1- The MCC rating at 50°C ambient temp. &IP43.
2- Operating voltage 400v.
3- Rated voltage l000v.
4- Short circuit for 1 sec 80 KA.
5- Bus bar should be copper material and insulated with silver plated for all contact area.
6-- All starters should be containing remote start-stop facility.
7- Motor starter drawable unit should be normal unit (fully modular) & small drawable unit (1/4 width, 1/2 width) not acceptable
8- MCCS supply with quantities.

Bidding Information

Bid Bond US 19,000.00
Bond Validity 120 days
Offer Validity 120 days
Documents Price ID 250,000.00
Electrical Works
Related Prooducts: Electrical Works Civil Works Civil Works - Finishing works Construction Contractors Electrical Works Engineering Procurement and Construction (EPC) Engineering Procurement and Construction Management (EPCM) General Mechanical Works Pipe Lines Installations Steel Works
Related Tenders: Civil Works Civil Works - Finishing works Construction Contractors Electrical Works Engineering Procurement and Construction (EPC) Engineering Procurement and Construction Management (EPCM) General Mechanical Works Pipe Lines Installations Steel Works

Related Articles

For Buyers
For Suppliers
Gulf Oil and Gas
Copyright © 2023 ICT All rights reserved. - Terms of Service - Privacy Policy.