- Construction and installation of Vali-1 leasepad facilities completed with mechanical handover to commissioning contractor
- First gas anticipated later in February
- Construction and installation of facilities ongoing at Vali-2 and Vali-3
- Project remains injury and environmental incident free
Vintage Energy Ltd (VEN, “Vintage”), 50% interest holder and Operator of the ATP 2021 joint venture
(other interest holders: Metgasco Ltd, 25%; and Bridgeport (Cooper Basin) Pty Ltd, 25%,) advises
commissioning of the gas production facilities at Vali-1 have commenced in preparation for first gas flows
from the field.
Background
The Vali gas field, discovered by the joint venture in 2020 is being connected to the South Australian
Cooper Basin gas gathering infrastructure to bring a new source of gas supply to eastern Australia. Vali
has been independently certified as having proved and probable gas reserves of 101 petajoules1
(PJ) (Vintage share 50.5 PJ). The joint venture has contracted to supply an estimated 9 PJ to 16 PJ gas to AGL from field start-up to end-2026.
The Vali gas project involves installation of metering facilities at the Vali facility, including separation
(located adjacent to Vali-1), installation of flowlines connecting the field’s three completed wells to the
metering facility, and twin export gas pipelines from the field to tie-in to the Moomba gas gathering
network at the Beckler gas field. Installation and pressure testing of the export flowlines was completed
successfully in December 2022. The Vali gas wells are to be connected and brought on-line progressively,
commencing with Vali-1, followed by Vali-3 and Vali-2.
Update
Mechanical handover of the facilities at Vali-1 took place on Saturday 11 February 2023, with control
passing to Upstream Production Solutions (UPS), the contractor engaged to commission, operate and
maintain the infrastructure.
Commissioning has commenced at Vali-1, starting with purging of the system with nitrogen to expel air
and various checks prior to the introduction of gas. This will be followed by commissioning of the metering
facility, Beckler tie-in and export lines. Subject to the progress of commissioning, it is projected first gas
from the field is likely in 7-12 days.
Construction and installation work is ongoing at the Vali-2 and Vali-3 sites. Mechanical handover and
commissioning at these locations is anticipated to occur by early March 2023.
Comment by Managing Director, Neil Gibbins
“The project transition from construction to commissioning marks a long-anticipated milestone for the
company and our shareholders. Vali is now one step away from first gas and with that the commencement
of revenue generation. Our focus is firmly on executing commissioning safely and efficiently so Vali gas
can start flowing to eastern Australia as soon as possible.
“On behalf of the board of directors, I would like to thank the contractor team, headed by Global
Engineering and Construction (“GEC)”, Hitec Electrical and Instrumentation (“HEI”) and others who have
worked at Vali, for the achievement of this milestone free of injuries and environmental incidents.
“We look forward to providing further updates on first gas, and the handover of the facilities at Vali-2 and
Vali-3 in due course” said Mr Gibbins.